I’ve 9.5 Update 3a and I have a issue/doubt.
Backups Jobs (BJ) run at night, with Full ones on Weekend. and BackCopy (BC) are running daily.
BC has several VMs lasting more than 24hrs to copy, so we’ve restricted this BC to run only between 5:00 and 22:00.
The BC repository is a USB/SharedFolder/CIFS location.
On first BC run it gave an warning but after restarting it resumed the Full copy but when reaching the 22:00 issued an error (why an error if it was expected to pause?)
Meanwhile normal BJ ran normally (although very very slow).
On resuming the BC at 5am instead of resuming the full restore point it started adding an incremental.
So this is how I have things now:
VM1: Full (ok – day1)
VM2: Full (Incomplete – day1) + Incremental (ok – day 2)
VM3: Full (Incomplete – day1) + Incremental (Incomplete – day 2) + Incremental (ok – day 3)
Questions:
a) Should not veeam resume the fulls for VM2 & 3?
b) Of course I cannot recover VM2 for day1. But, for sure, may I entirely recover VM2 from day 2 on?
c) The same for VM3, cannot recover day1 & day2 but recover from day3 forward?
All the best
Paulo Balau