Veeam Logoby msp » Fri Apr 10, 2015 10:20 am

Hello

I am confused to how the Backup and Replication Job Status dashboard work.
I have 10 backup jobs and 10 copy jobs running over the evening and night everyday, and my Data collection in the morning.
The issue is that my dashboard rarely shows all 20 jobs on the chart for one day.
Today for exsample i have 10 completet jobs on the chart, and if i drill down in the chart, it shows 10 completed backup jobs and that the copy jobs are idle. I went to the backup server to check the idle copy jobs, and they have been running and completed, but the status are idle.

So my question is, when does the idle copy jobs show up on the dashboard chart as completed?
msp
Lurker
 
Posts: 2
Liked: never
Joined: Fri Apr 10, 2015 9:20 am

Re: Dashboard - Backup and Replication Job Status

Veeam Logoby Shestakov » Fri Apr 10, 2015 11:10 am

Hello and welcome to the forums!
Do you see those backup jobs completed if you make full report with Last 24 hours interval set?
To make sure if the widget works fine, you can find a backup copy job in VBR UI and click "Report" to see when the job was finished.
By default, Job Status widget shows current week`s statistics, however you can set desired interval in the drill-down report.
Thanks!
Shestakov
Veeam Software
 
Posts: 4856
Liked: 394 times
Joined: Wed May 21, 2014 11:03 am
Location: Saint Petersburg
Full Name: Nikita Shestakov

Re: Dashboard - Backup and Replication Job Status

Veeam Logoby Vitaliy S. » Fri Apr 10, 2015 4:10 pm

Something tells me that this dashboard will always show idle for all completed backup copy jobs, as technical it is exactly their current state. Let me ask to confirm this behavior and I will post back.
Vitaliy S.
Veeam Software
 
Posts: 19556
Liked: 1101 times
Joined: Mon Mar 30, 2009 9:13 am
Full Name: Vitaliy Safarov

Re: Dashboard - Backup and Replication Job Status

Veeam Logoby Vitaliy S. » Fri Apr 10, 2015 7:35 pm

Yes, this is what I thought. The drill down report, indeed, shows "idle" as a latest state for configured backup copy jobs. Thanks for the heads up!
Vitaliy S.
Veeam Software
 
Posts: 19556
Liked: 1101 times
Joined: Mon Mar 30, 2009 9:13 am
Full Name: Vitaliy Safarov

Re: Dashboard - Backup and Replication Job Status

Veeam Logoby msp » Wed Apr 15, 2015 8:24 am

I been testing it for a few days. here is what i found out so far.

The copy jobs will be displayed as idle until a new copy job Begins, then it will show as completet at the dashboard chart.
I dont understand why it is designed like that. Maybe im doing something worng, but the result is that the copy jobs are one day behind, when it comes to be displayed at the dashboard chart.

so right now my dashboard shows :
Monday 20 completed jobs (backup jobs and copy jobs)
Tuesday 10 completed jobs (only backup jobs shows, the copy jobs are done but are in idle state)

Is there a way to fix this?
msp
Lurker
 
Posts: 2
Liked: never
Joined: Fri Apr 10, 2015 9:20 am

Re: Dashboard - Backup and Replication Job Status

Veeam Logoby Vitaliy S. » Wed Apr 15, 2015 10:50 am

msp wrote:I dont understand why it is designed like that. Maybe im doing something worng, but the result is that the copy jobs are one day behind, when it comes to be displayed at the dashboard chart.

That's a bug, as I've stated in my previous post. Please open a support case with our technical stuff, and our dev will work on the private hotfix for this issue.
Vitaliy S.
Veeam Software
 
Posts: 19556
Liked: 1101 times
Joined: Mon Mar 30, 2009 9:13 am
Full Name: Vitaliy Safarov


Return to Reporting



Who is online

Users browsing this forum: No registered users and 4 guests