Hi all,
In a GFS tape job, i actually have a tape media whose expiration date is 3 days later (more or less) than the scheduled backup date.
Is there any way to change this tape media expiration date in order to have the job started on the scheduled day?
Or shall i erase the tape and add back to the job as a new tape, then use it?
-
- Influencer
- Posts: 16
- Liked: never
- Joined: Feb 05, 2021 4:09 pm
- Contact:
-
- Product Manager
- Posts: 14726
- Liked: 1707 times
- Joined: Feb 04, 2013 2:07 pm
- Full Name: Dmitry Popov
- Location: Prague
- Contact:
Re: Change tape Expiration Date
Hello AVLoki,
You can change the retention in the media pool properties but it will affect all the tapes in the media pool.Is there any way to change this tape media expiration date in order to have the job started on the scheduled day?
That looks like the best workaround. Cheers!Or shall i erase the tape and add back to the job as a new tape, then use it?