- Novice
- Posts: 3
- Liked: never
- Joined: Mar 07, 2017 11:23 am
- Full Name: ITCC
- Contact:
Feature Request -- Multiple Libararies Parallel Processing
-- Feature Request -- Case # 0208972
Parallel Processing Backup to Tape with Multiple Libararies (Two Physical Tape Libararies )
at the moment is only possibile "Parallel Processing Backup to Tape with one Library (Multiple Tape Drives)
Br
Sven Bahr
Parallel Processing Backup to Tape with Multiple Libararies (Two Physical Tape Libararies )
at the moment is only possibile "Parallel Processing Backup to Tape with one Library (Multiple Tape Drives)
Br
Sven Bahr
-
- Product Manager
- Posts: 20415
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Feature Request -- Multiple Libararies Parallel Processi
It's already possible if you have more than one backup to tape job. Thanks.Parallel Processing Backup to Tape with Multiple Libararies
-
- Novice
- Posts: 3
- Liked: never
- Joined: Mar 07, 2017 11:23 am
- Full Name: ITCC
- Contact:
Re: Feature Request -- Multiple Libararies Parallel Processi
we have one job to tape and one Media Pool. We haveTwo Physical Tape Libararies we need to backup simultaneously!
Br.
Br.
-
- Product Manager
- Posts: 20415
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Feature Request -- Multiple Libararies Parallel Processi
You might want to create additional job to leverage two libraries simultaneously.
Currently, it is not possible to utilize several libraries within one tape job, and up to the moment we have not received enough requests to justify this enhancement in version 10.
Thanks.
Currently, it is not possible to utilize several libraries within one tape job, and up to the moment we have not received enough requests to justify this enhancement in version 10.
Thanks.
-
- Novice
- Posts: 3
- Liked: never
- Joined: Mar 07, 2017 11:23 am
- Full Name: ITCC
- Contact:
Re: Feature Request -- Multiple Libararies Parallel Processi
if i create a "Tape Job- Backup to Tape" twice with the same settins and VM's will solve the problem?v.Eremin wrote:You might want to create additional job to leverage two libraries simultaneously.
Thanks, Sven
-
- Product Manager
- Posts: 14726
- Liked: 1707 times
- Joined: Feb 04, 2013 2:07 pm
- Full Name: Dmitry Popov
- Location: Prague
- Contact:
Re: Feature Request -- Multiple Libararies Parallel Processi
Yes, that should work. Failover for event ‘all drives are busy’ performs a drive check at the beginning of the tape job. If all drives from the first library are locked , job will be forced to use second device.
-
- VP, Product Management
- Posts: 7081
- Liked: 1511 times
- Joined: May 04, 2011 8:36 am
- Full Name: Andreas Neufert
- Location: Germany
- Contact:
Re: Feature Request -- Multiple Libararies Parallel Processi
Support Case: 02089723 (Feature Request)
-
- Veeam Software
- Posts: 622
- Liked: 63 times
- Joined: Jan 07, 2013 9:26 am
- Full Name: Markus Hergt
- Location: Germany
- Contact:
Re: Feature Request -- Multiple Libararies Parallel Processi
attention:ITCC wrote:
if i create a "Tape Job- Backup to Tape" twice with the same settins and VM's will solve the problem?
Thanks, Sven
both Backup2Tape jobs have to splitted from a content point of view, otherwise all Data would be stored twice on the tapes....
so in summary:
create 2 Backup2Tape jobs, and split the vm's between the 2 jobs
Who is online
Users browsing this forum: No registered users and 6 guests