GFS Backup Job
Currently I have 1 GFS media pool and only enabled for Weekly retention for 2 weeks. I'm going to create a tape backup job and about to set it to run every Sunday of the week. I've the below questions and appreciate if anyone could advise on these:
1. I can set the job to run Weekly only but what does the daily scan in tape job means? Can I specify the exact time to run the weekly backup on Sunday?
2. If I set it to run weekly, every time it will be a Full Backup/Synthetic?
1. I can set the job to run Weekly only but what does the daily scan in tape job means? Can I specify the exact time to run the weekly backup on Sunday?
2. If I set it to run weekly, every time it will be a Full Backup/Synthetic?
-
- Product Manager
- Posts: 14839
- Liked: 3086 times
- Joined: Sep 01, 2014 11:46 am
- Full Name: Hannes Kasparick
- Location: Austria
- Contact:
Re: GFS Backup Job
Hello,
1. Can you maybe explain a little bit more what kind of scan you mean. I also have GFS jobs, but no scan in my session history. If the question is about multiple restore points, then the answer is given in point 2
2. You have a full, yes. Whether it's synthetic or not depends when / whether your backup jobs generate fulls: point 2
Best regards,
Hannes
1. Can you maybe explain a little bit more what kind of scan you mean. I also have GFS jobs, but no scan in my session history. If the question is about multiple restore points, then the answer is given in point 2
2. You have a full, yes. Whether it's synthetic or not depends when / whether your backup jobs generate fulls: point 2
Best regards,
Hannes
-
- Enthusiast
- Posts: 49
- Liked: 3 times
- Joined: Jul 02, 2021 3:42 am
- Full Name: Markus
- Contact:
Re: GFS Backup Job
Hi Hannesk,
For no.1, according to the url. Does the below concept correct?
I have a gfs media set and I only enable weekly which means the daily has been disabled. So when I create a gfs job, it will perform a full backup the first time I run it. And then according to my VM Backup job, I have synthetic backup on every Saturday. My tape job weekly set to run on every Sunday. So in this case, when the tape job runs it will detect there's a new synthetic full backup so it will take that full backup into tape. Is this the correct understanding?
For no.2, seems like the same concept as above.
Please correct me if I'm wrong. Thank you so much.
For no.1, according to the url. Does the below concept correct?
I have a gfs media set and I only enable weekly which means the daily has been disabled. So when I create a gfs job, it will perform a full backup the first time I run it. And then according to my VM Backup job, I have synthetic backup on every Saturday. My tape job weekly set to run on every Sunday. So in this case, when the tape job runs it will detect there's a new synthetic full backup so it will take that full backup into tape. Is this the correct understanding?
For no.2, seems like the same concept as above.
Please correct me if I'm wrong. Thank you so much.
-
- Product Manager
- Posts: 14839
- Liked: 3086 times
- Joined: Sep 01, 2014 11:46 am
- Full Name: Hannes Kasparick
- Location: Austria
- Contact:
Re: GFS Backup Job
Hello,
1. as you probably have another increment on Sunday it will
Best regards,
Hannes
1. as you probably have another increment on Sunday it will
2. yepuser guide point 2 wrote:If the source job creates an incremental backup, the GFS job synthesizes a virtual full backup.
Best regards,
Hannes
-
- Enthusiast
- Posts: 49
- Liked: 3 times
- Joined: Jul 02, 2021 3:42 am
- Full Name: Markus
- Contact:
Re: GFS Backup Job
Hi Hannesk,
As I read through below article it seems like the virtual full backup is only used in forever forward incremental? My VM backup job configured as forward incremental backup only so is this still apply to my situation?
https://helpcenter.veeam.com/docs/backu ... ml?ver=110
As I read through below article it seems like the virtual full backup is only used in forever forward incremental? My VM backup job configured as forward incremental backup only so is this still apply to my situation?
https://helpcenter.veeam.com/docs/backu ... ml?ver=110
-
- Product Manager
- Posts: 14839
- Liked: 3086 times
- Joined: Sep 01, 2014 11:46 am
- Full Name: Hannes Kasparick
- Location: Austria
- Contact:
Re: GFS Backup Job
the article you point to is for standard media pools. In your first post I read that you use a GFS media pool. GFS and standard pools behave different.
-
- Enthusiast
- Posts: 49
- Liked: 3 times
- Joined: Jul 02, 2021 3:42 am
- Full Name: Markus
- Contact:
Re: GFS Backup Job
Oh I see, yes I'm using GFS media pools. So since my normal backup job will do incremental everyday except Saturday. When my tape job runs on Wednesday for example, it will do a virtual full backup for second time right
-
- Product Manager
- Posts: 14720
- Liked: 1705 times
- Joined: Feb 04, 2013 2:07 pm
- Full Name: Dmitry Popov
- Location: Prague
- Contact:
Re: GFS Backup Job
Hello Markus,
Backup to daily media set (if read question correctly) takes all the backups files from the repository: incrementals and full backups. Backup to weekly media set will process only full backups (or create a synthesized full backup for the set day if you dont have a full backup on disk).1. I can set the job to run Weekly only but what does the daily scan in tape job means?
You can select the gfs tape job start time, yes.Can I specify the exact time to run the weekly backup on Sunday?
Yes, weekly, monthly, quarterly and yearly tape out only full backup from disk and when it's not present create a synthesized full backup from incremental restore point.2. If I set it to run weekly, every time it will be a Full Backup/Synthetic?