Discussions related to exporting backups to tape and backing up directly to tape.
Post Reply
Steen
Service Provider
Posts: 51
Liked: 3 times
Joined: Mar 13, 2015 1:20 pm
Full Name: Steen
Contact:

Only 1 Tape-job per day

Post by Steen »

if there is a full backup-job made this day and and some incrementals after that Tape-job only take the full.
2015-05-22 17:59:01 :: Processing full backup of A test
2015-05-22 18:05:50 :: Processing incremental backup of A test: nothing to backup
2015-05-22 18:05:50 :: 0 directories and 1 files backed up successfully

This is a new job made this day with 1 full and 2 incrementals
regards Steen
Regards Steen
Shestakov
Veteran
Posts: 7328
Liked: 781 times
Joined: May 21, 2014 11:03 am
Full Name: Nikita Shestakov
Location: Prague
Contact:

Re: Only 1 Tape-job per day

Post by Shestakov »

Hello Steen,
Have you set backup to tape job to copy both fulls and increments? Thanks!
Steen
Service Provider
Posts: 51
Liked: 3 times
Joined: Mar 13, 2015 1:20 pm
Full Name: Steen
Contact:

Re: Only 1 Tape-job per day

Post by Steen »

Shestakov wrote:Hello Steen,
Have you set backup to tape job to copy both fulls and increments? Thanks!
No.
only full (and checked synthetic on every day)
Regards Steen
Shestakov
Veteran
Posts: 7328
Liked: 781 times
Joined: May 21, 2014 11:03 am
Full Name: Nikita Shestakov
Location: Prague
Contact:

Re: Only 1 Tape-job per day

Post by Shestakov »

You created a source job with 1 Full + 2 Increments, set the backup to tape job to copy Fulls only and as a result one Full backup is copied. Is it correct? If yes, what is your concern?
Thanks!
Steen
Service Provider
Posts: 51
Liked: 3 times
Joined: Mar 13, 2015 1:20 pm
Full Name: Steen
Contact:

Re: Only 1 Tape-job per day

Post by Steen »

Shestakov wrote:You created a source job with 1 Full + 2 Increments, set the backup to tape job to copy Fulls only and as a result one Full backup is copied. Is it correct? If yes, what is your concern?
Thanks!
i also checked synthetic backup... but none was made...
Regards Steen
Treeeman
Enthusiast
Posts: 70
Liked: 1 time
Joined: Apr 18, 2014 11:30 am
Contact:

Re: Only 1 Tape-job per day

Post by Treeeman »

Hello,

what Version are you using?

What i have seen:
If you use Veeam v8 prior update 2 you have to enable syntetic full for the days you want and additionally enable the checkbox to process incremental Backup Files within your Tape Job.
If you using the actual Version 8 with update 2 installed you don't have to enable the checkbox to process incremental Files.

KR
Marco
Steen
Service Provider
Posts: 51
Liked: 3 times
Joined: Mar 13, 2015 1:20 pm
Full Name: Steen
Contact:

Re: Only 1 Tape-job per day

Post by Steen »

Treeeman wrote:Hello,

what Version are you using?

What i have seen:
If you use Veeam v8 prior update 2 you have to enable syntetic full for the days you want and additionally enable the checkbox to process incremental Backup Files within your Tape Job.
If you using the actual Version 8 with update 2 installed you don't have to enable the checkbox to process incremental Files.

KR
Marco
Patch 2
Regards Steen
Treeeman
Enthusiast
Posts: 70
Liked: 1 time
Joined: Apr 18, 2014 11:30 am
Contact:

Re: Only 1 Tape-job per day

Post by Treeeman »

I am not sure what your problem is.
Do i understand right that Veeam only store your first VBK File on tape and not the syntetic full from the last restore Point?

Maybe you can clarify your issue a litte bit further.
Steen
Service Provider
Posts: 51
Liked: 3 times
Joined: Mar 13, 2015 1:20 pm
Full Name: Steen
Contact:

Re: Only 1 Tape-job per day

Post by Steen »

Treeeman wrote:I am not sure what your problem is.
Do i understand right that Veeam only store your first VBK File on tape and not the syntetic full from the last restore Point?

Maybe you can clarify your issue a litte bit further.
if you make a full backup now and make tape same day and after that you make make incremental backup.

Now you You want a full SYNTHETIC backup.
But it says nothing to backup.
Regards Steen
Treeeman
Enthusiast
Posts: 70
Liked: 1 time
Joined: Apr 18, 2014 11:30 am
Contact:

Re: Only 1 Tape-job per day

Post by Treeeman »

Ok. From my understanding from Syntetic full to tape you are right. I would also expect a Full Syntetic Backup to tape, because there is a newer (incremental) Restore Point.

I see something similar to this sometimes with Syntetic full.
Forward Incremental Forever at 20:00 PM. Backup to Tape at 23:00 PM. Sometimes i am getting the Message "No Restore Points found" or "No new file".
But in fact there is a new (incremental) Restore Point created at 20:00 PM.
veremin
Product Manager
Posts: 20270
Liked: 2252 times
Joined: Oct 26, 2012 3:28 pm
Full Name: Vladimir Eremin
Contact:

Re: Only 1 Tape-job per day

Post by veremin »

Just to clarify, there is a incremental point created by source backup job on a given day, there is backup to tape job that has the said backup job as its source, virtual full backup is enabled in the setting of the tape job and its creation date coincides with creation time of the mentioned restore point, when you execute tape job it fails, instead of creating virtual full backup, right?
Treeeman
Enthusiast
Posts: 70
Liked: 1 time
Joined: Apr 18, 2014 11:30 am
Contact:

Re: Only 1 Tape-job per day

Post by Treeeman »

Yes, there is a new incremental point by source backup job.
Yes, backup to tape job with said backup job as its source.
Yes, Virtual full backup enabled from monday to sunday.

If i execute tape job (not matter if scheduled or manually) the VM is processed and marked as "Success". But if i click at the VM there is only the Message "No Restore Points found".
veremin
Product Manager
Posts: 20270
Liked: 2252 times
Joined: Oct 26, 2012 3:28 pm
Full Name: Vladimir Eremin
Contact:

Re: Only 1 Tape-job per day

Post by veremin »

Open a ticket with our support team and let them investigate it directly. Thanks.
Post Reply

Who is online

Users browsing this forum: No registered users and 13 guests