Take a Full tape backup outside of the schedule

Post by stewsie »

Hi

We had some issues that caused a number of tape jobs to fail some of which were full backups. Is it possible to force a Full tape job to run without manually changing the day the Full would normally be taken?

Thanks
Dima P.
Product Manager
Posts: 14716
Liked: 1702 times
Joined: Feb 04, 2013 2:07 pm
Full Name: Dmitry Popov
Location: Prague
Contact:

Re: Take a Full tape backup outside of the schedule

Post by Dima P. »

Hello Paul,

Can you please clarify if these jobs are pointed to GFS media pool or regular media pool? Thanks!
stewsie
Veteran
Posts: 282
Liked: 25 times
Joined: May 22, 2015 7:16 am
Full Name: Paul
Contact:

Re: Take a Full tape backup outside of the schedule

Post by stewsie »

Regular media pool. We have two pools configured. One for Full and the other for Incremental
Dima P.
Product Manager
Posts: 14716
Liked: 1702 times
Joined: Feb 04, 2013 2:07 pm
Full Name: Dmitry Popov
Location: Prague
Contact:

Re: Take a Full tape backup outside of the schedule

Post by Dima P. » 1 person likes this post

Thanks for the clarification. Tape job pointed to the regular media pool can only create synthesized full backup based on the schedule. You can test GFS tape jobs (tape jobs pointed to a GFS media pool) as they do provide the ability to create Full backup to any media set whenever its required.
stewsie
Veteran
Posts: 282
Liked: 25 times
Joined: May 22, 2015 7:16 am
Full Name: Paul
Contact:

Re: Take a Full tape backup outside of the schedule

Post by stewsie »

Thanks I will investigate