Hello
I would like to set up tape migrations to full and incremental backups using different media pools to different tape libraries.
The Veeam backup jobs run on weekdays only (Mon-Fri). They are forever incremental jobs.
The tape migration for full backups would be at the weekend (Sat-Sun).
The tape migration for incremental backups would be weekdays (Mon-Fri).
How do I set up the tape migrations to ensure that the full backup migration runs on the weekend and the incremental backup migrations run during the week?
As a note we are upgrading to Veeam 9.5 on Thursday 4th May 2017 and will be moving to REFS repositories.
Many thanks.
Andrew
-
- Enthusiast
- Posts: 33
- Liked: 2 times
- Joined: Oct 29, 2016 10:13 pm
- Full Name: Andrew Fox
- Contact:
-
- Product Manager
- Posts: 14818
- Liked: 1772 times
- Joined: Feb 04, 2013 2:07 pm
- Full Name: Dmitry Popov
- Location: Prague
- Contact:
Re: Tape Full and Incremental
Hello Andrew,
Just to clarify, you want to write your backup file to two separate tape devices. For each tape device you plan to create a media pool, one is going to be used for full backup files and another for incremental only, right? Thank you.
Just to clarify, you want to write your backup file to two separate tape devices. For each tape device you plan to create a media pool, one is going to be used for full backup files and another for incremental only, right? Thank you.
-
- Enthusiast
- Posts: 33
- Liked: 2 times
- Joined: Oct 29, 2016 10:13 pm
- Full Name: Andrew Fox
- Contact:
Re: Tape Full and Incremental
Hello
Yes, that is correct. I need to make sure the full go to a media pool on the weekend and the incremental go to the other media pool during the week,
Andrew
Yes, that is correct. I need to make sure the full go to a media pool on the weekend and the incremental go to the other media pool during the week,
Andrew
-
- Enthusiast
- Posts: 33
- Liked: 2 times
- Joined: Oct 29, 2016 10:13 pm
- Full Name: Andrew Fox
- Contact:
Re: Tape Full and Incremental
Hello
Any ideas on this as I would like to begin as soon as possible.
Thanks Andrew
Any ideas on this as I would like to begin as soon as possible.
Thanks Andrew
-
- Product Manager
- Posts: 20677
- Liked: 2382 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Tape Full and Incremental
- Create two media pools ("Full" and "Incremental")
- Create a backup to tape job
- Select forward forever incremental backup job as its source
- Select corresponding media pools ("Full" for fulls, "Incremental" for increments)
- Schedule the job to run on everyday basis, selecting Saturday and Sunday as virtual full backup creation dates
- Create a backup to tape job
- Select forward forever incremental backup job as its source
- Select corresponding media pools ("Full" for fulls, "Incremental" for increments)
- Schedule the job to run on everyday basis, selecting Saturday and Sunday as virtual full backup creation dates