Hi,

In the scheduler settings we got the option "Terminate job if it exceed the allowed windows".

Will it create a consistend restore point of the finished items? Or will it discard?

Regards
Service Provider | VMCE
Polina
Veeam Software
Posts: 3456
Liked: 828 times
Joined: Oct 21, 2011 11:22 am
Full Name: Polina Vasileva

Re: Terminate job if it exceed...

Post by Polina »

Hi Manuel,

A terminated job is similar to a stopped job - no restore point is created.