Veeam Logoby MikaelG » Fri Dec 30, 2016 9:11 pm

Hi,

I have 2 jobs covering the same VM. One runs 3 times a day and it keeps restore points to cover 1 week. The other job runs each night and it keeps restore point for 3 months. Now I would like to set up a backup copy job that copies the latest restore point from either job. And that it does it right after the jobs finnishes. I´ve tried to set the backup copy jobs cycle to 1 per hour but then it never finds an up-to-date restore point. If I set the cycle to once a day it does find a restore point but only copies once a day? So how can I achieve what I want?

Thanks,

Mikael
MikaelG
Influencer
 
Posts: 13
Liked: 1 time
Joined: Wed Dec 21, 2016 9:43 am
Full Name: Mikael Gustafsson

Re: Backup Copy cycles

Veeam Logoby EugeneK » Fri Dec 30, 2016 10:41 pm

Hi Mikael,

Backup Copy Job will search for the latest restore point for a VM and use it to process data. The process is well described at
https://helpcenter.veeam.com/docs/backu ... tml?ver=95
and
https://helpcenter.veeam.com/docs/backu ... tml?ver=95

When you configured it to run daily, the latest restore point got copied over as expected, then it declares "already processed this VM Copy today".
If you set the interval to more frequent one, lets say hourly, it should have found the restore point. I'd recommend to check the logs for both, primary and Copy backup jobs and correlate the status of files and timestamps and see if the files weren't in consumable state.
Eugene K
Product Architect @ SingleHop - Veeam Platinum Service Provider
http://www.singlehop.com
VCAP-DCD, VCAP-DCA, VCP-NV
Veeam Certified Architect
EugeneK
Veeam Vanguard
 
Posts: 102
Liked: 23 times
Joined: Sat Mar 19, 2016 10:57 pm
Location: Chicago, IL
Full Name: Eugene Kashperovetskyi

Re: Backup Copy cycles

Veeam Logoby MikaelG » Sat Dec 31, 2016 9:19 am

Thanks , I'll look at those links. However I think I remember reading that there is some calculation being done to find the restore Pont. Time of day > resroepoint - cycle. I don't remember exactly, but when I set the cycle to hourly it didn't find anything. I'll read the links and see if I understand better, thanks.
MikaelG
Influencer
 
Posts: 13
Liked: 1 time
Joined: Wed Dec 21, 2016 9:43 am
Full Name: Mikael Gustafsson

Re: Backup Copy cycles

Veeam Logoby MikaelG » Mon Jan 02, 2017 10:29 am

I´ve read that link again and I according the calcutalion Veeam makes it should copy the restore point created latest but it doesn´t. It just says latest restore point already copied. I´ll open a case to get it sorted.
MikaelG
Influencer
 
Posts: 13
Liked: 1 time
Joined: Wed Dec 21, 2016 9:43 am
Full Name: Mikael Gustafsson

Re: Backup Copy cycles

Veeam Logoby Andreas Neufert » Mon Jan 02, 2017 11:20 pm

Maybe root cause is that the BCJ target is the same repositories as one of your BCJ source repositories?
Please updated this thread with the case number. Thank you.
Andreas Neufert
Veeam Software
 
Posts: 2266
Liked: 376 times
Joined: Wed May 04, 2011 8:36 am
Location: Germany
Full Name: @AndyandtheVMs Veeam PM

Re: Backup Copy cycles

Veeam Logoby foggy » Tue Jan 03, 2017 12:26 pm

Hi Mikael, I also wonder how have you added the VM to the backup copy job? And what is your goal with this backup copy - do you want it to copy every restore point produced by both backup jobs?
foggy
Veeam Software
 
Posts: 15089
Liked: 1110 times
Joined: Mon Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson


Return to Veeam Backup & Replication



Who is online

Users browsing this forum: Bing [Bot], deltavictor, PParkin and 80 guests