Hello,
I have a problem with backup job periodically.
I need to start a job every 8 hours from 4 AM to 9 PM.
I wish the job were run at 4 AM, 12 PM, 8 PM.
On my job I checked "run the job automatically" and I selected "periodically every" and insert 8 on first field and I selected Hours. On schedule bottom I permitted from 4.00 AM to 8.59 PM.
My job run on 6 PM and 10 AM
Someone can help me ?
-
- Influencer
- Posts: 19
- Liked: never
- Joined: Sep 27, 2011 12:41 pm
- Full Name: Manuel Righi
- Contact:
-
- Product Manager
- Posts: 20415
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Backup job periodically
Is it possible that you specified the aforesaid schedule when there was like 5+ pm and the closest full hour was taken as a time for running job?
Thanks.
Thanks.
-
- Influencer
- Posts: 19
- Liked: never
- Joined: Sep 27, 2011 12:41 pm
- Full Name: Manuel Righi
- Contact:
Re: Backup job periodically
yes, is possible.v.Eremin wrote:Is it possible that you specified the aforesaid schedule when there was like 5+ pm ? In this case the closest full hour was taken as a time for running job.
Thanks.
I then recreate the job outside the backup window (ie after 8:59 PM) ?
-
- Product Manager
- Posts: 20415
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Backup job periodically
If you recreate a job outside a backup schedule, in this case the first permitted hour will be chosen as a time for a job run. So, it seems to be exactly what you’re after.