Hi All,
We’re using a SOBR with a performance tier locally, and Backblaze as our capacity extent.
Unfortunately ReFS is not so resilient, and we lost our local performance repository. (Despite BBU on our RAID controller, a power outage took out the ReFS global table).
Anyhow…. Best practice question: recreate the performance tier, remove the old performance tier and add the new performance tier to the SOBR? Then do an active full?
Any input is greatly appreciated. I have object locking on the BackBlaze tier and retention is set to 30 days, with forward incrementals. I’m hoping not to cause a large usage spike in BackBlaze. Should I put the the capacity extent in maintenance mode for a while?
Thank you in advance!
-
- Influencer
- Posts: 23
- Liked: 1 time
- Joined: Dec 16, 2009 12:50 am
- Contact:
-
- Influencer
- Posts: 23
- Liked: 1 time
- Joined: Dec 16, 2009 12:50 am
- Contact:
Re: Best practice for lost Performance Extent
Also, I neglected to mention we are using forever forward incrementals