We've noticed that the status of tasks relating to a job that's disabled is being reported as 'Warning' rather than 'Failed'. Just wondered what people's thoughts are on this and whether its right.
The Veeam licence usage report includes all tasks with status of 'success' or 'warning' which seems to suggest these are seen as a backup having been completed on that VM and therefore a licence should be purchased. Surely if the job is disabled that shouldn't be the case.
-
- Lurker
- Posts: 1
- Liked: never
- Joined: May 27, 2014 10:37 am
- Contact:
-
- Product Manager
- Posts: 20413
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Classification of disabled jobs
Backup server releases a license assigned to VM, if it has been processed within last 31 days. Backup job state doesn't matter here. Thanks!