Exchange Restore: spread out DC and Exchange restore points

Post by keatho » Mar 31, 2011 11:24 pm

Hello,

I have a backup of my Domain Controller with restore points back to 26th March and a backup of my Exchange Server with restore points going back to 10th March. Both servers are in different backup jobs.
Am i able to add these two servers into an Application Group and choose the Surebackup Job option 'Start Job To' and select the 10th March ?

I am trying to restore a mailbox from 10th March and need the DC to be powered on in the Virtual Lab.

DC - Win 2003
Exc 2007
Veeam 5.0

Thankyou

Gostev
SVP, Product Management
Posts: 24825
Liked: 3578 times
Joined: Jan 01, 2006 1:01 am
Location: Baar, Switzerland
Contact:

Re: Exchange Restore

Post by Gostev » Mar 31, 2011 11:34 pm

Yes, this should work. The job will use DC backup closest to select date. The only potential issue I see is Exchange and DC being too out of sync. For example, Exchange server computer account password might have been changed since March 10th. Thanks.

keatho
Novice
Posts: 6
Liked: never
Joined: Mar 31, 2011 11:14 pm
Full Name: Jye Keath
Contact:

Re: Exchange Restore

Post by keatho » Apr 04, 2011 5:21 am

Thanks for the reply Gostev,

I ran the job and it was successful.