Feature request: keep SureBackup VMs running if tests fail

Post by jb238 »

In the SureBackup Job in chapter "Application Group" there is a setting "Keep the application group running after the job completes".
This works only, if the tests are successful.
If some of the tests fail, the VMs are stopped and removed. This makes debugging what went wrong impossible.
The session log in the GUI is very rudimentary and the VMs are no longer available for detailed inspection.
I'd like to have some setting to terminate the VMs if everything is ok and to keep them running if a test fails so I can find out exactly what went wrong.

I reported this as case 02356547 and it was suggested that I add this here as a feature request.
foggy
Veeam Software
Posts: 21139
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Feature request: keep SureBackup VMs running if tests fa

Post by foggy »

Hi Joerg, thanks for the feedback, your request is accepted and much appreciated.