If you already have existing jobs and you add in a new server into the schedule, are you forced to run a full backup on that scheduled job or will a full backup of the newly added server be taken during the next scheduled backup?
-
- Enthusiast
- Posts: 29
- Liked: never
- Joined: Jan 27, 2010 1:03 pm
- Full Name: Richard Wallis
- Contact:
-
- VP, Product Management
- Posts: 27371
- Liked: 2799 times
- Joined: Mar 30, 2009 9:13 am
- Full Name: Vitaliy Safarov
- Contact:
Re: first backup
Hi Richard, the full backup of the newly added VMs will be taken automatically during the next scheduled job run. Thanks!
-