How to backup with a V-Lab running
Hello, I'm testing the V-Lab functionalties and I'm very confused on this point: if I start a SureBackup Job and keep it running every time the scheduled backup job starts it fails with the error "The process cannot access the file because it is being used by another process. Failed to create or open file..."
Is there anyway to keep the SB Job running and continue to have the normal backup job running?
Thank you.
Is there anyway to keep the SB Job running and continue to have the normal backup job running?
Thank you.
-
- Product Manager
- Posts: 6551
- Liked: 765 times
- Joined: May 19, 2015 1:46 pm
- Contact:
Re: How to backup with a V-Lab running
Hi,
Thank you.
That happens because SureBackup job runs a VM directly from a backup file thus locking it from being accessed by other processes.if I start a SureBackup Job and keep it running every time the scheduled backup job starts it fails with the error "The process cannot access the file because it is being used by another process. Failed to create or open file..."
What backup policy do you use?Is there anyway to keep the SB Job running and continue to have the normal backup job running?
Thank you.
-
- Novice
- Posts: 9
- Liked: never
- Joined: Dec 23, 2015 2:00 pm
- Full Name: kinto
- Contact:
Re: How to backup with a V-Lab running
Hello Ptide, I have a simple Incremental backup policy.
I have also scheduled the job from Tuesday to Saturday at 4.00 am.
I have also scheduled the job from Tuesday to Saturday at 4.00 am.
-
- Product Manager
- Posts: 6551
- Liked: 765 times
- Joined: May 19, 2015 1:46 pm
- Contact:
Re: How to backup with a V-Lab running
May I ask you which version are you running? I suggest you to open a case with support, because Backup jobs should have higher priority and thus are supposed to stop any other job that is locking the backup file for writing. The fact that Surebackup job prevents backup job from running is an unexpected behaviour and log investigation is needed. Please don't forget to post your case ID here.
Also may I ask you why do you need your SureBackup to be runnning simultaneously with backup job?
Thank you.
Do you mean "Forever Incremental"? If so then technically, it's not possible with such policy. You need to schedule periodic fulls so your SureBackup job does not lock the trailing .vbk but uses the most recent full. In that case SureBackup job won't interfere with merging process.simple Incremental backup policy.
Also may I ask you why do you need your SureBackup to be runnning simultaneously with backup job?
Thank you.
-
- Novice
- Posts: 9
- Liked: never
- Joined: Dec 23, 2015 2:00 pm
- Full Name: kinto
- Contact:
Re: How to backup with a V-Lab running
Current version is 8.0.0.208 and yes actually the configuration is forevere incremental.
To solve this problem colud be a solution to have synthethic full backups from monday to friday and an active full backup at saturday?
I need the V-Lab running also during backup jobs because there is a software house that periodically needs a copy of the VMs at some point in time to test software patches also for a long period of time.
Thank you.
To solve this problem colud be a solution to have synthethic full backups from monday to friday and an active full backup at saturday?
I need the V-Lab running also during backup jobs because there is a software house that periodically needs a copy of the VMs at some point in time to test software patches also for a long period of time.
Thank you.
-
- Product Manager
- Posts: 6551
- Liked: 765 times
- Joined: May 19, 2015 1:46 pm
- Contact:
Re: How to backup with a V-Lab running
All you need is just one periodic full, no matter of what type it will be.To solve this problem colud be a solution to have synthethic full backups from monday to friday and an active full backup at saturday?
You'll need to restart your VMs once in a while because your vPower NFS will eventually get filled with changes that happen to VMs inside lab. I think it would be better to spin-up the lab on demand (after patches) or to try this approachI need the V-Lab running also during backup jobs because there is a software house that periodically needs a copy of the VMs at some point in time to test software patches also for a long period of time.
Kindly open a case with support and post your ID here - we would like to investigate the issue with job priorities.