How to copy all restore points in copy job ?

Post by cybava »

Hi,

I use Veeam V8 on a physical server on a datacenter and i have somes backups jobs (daily, weekly, monthly) with disk storage
My jobs was on reverse incremental and i juste changed it for incremental
I would like to have an exact copy of my backups on an other site.
I try to setup a copy job but it copy only the last increment.

Example:

I have a monthly job for my file server with 24 retention points. So i have 2 years backup.
When i use the copy job, it only copy the last retention point, so i need 24 cycle of copy job to have the same things on the 2 sides
IS there a way to copy all old retention point with the copy job ?

Thanks !
veremin
Product Manager
Posts: 20415
Liked: 2302 times
Joined: Oct 26, 2012 3:28 pm
Full Name: Vladimir Eremin
Contact:

Re: How to copy all restore points in copy job ?

Post by veremin »

Backup copy job doesn't t copy backup chain as a whole, but rather synthetically creates required restore points in "target" location from VM data in source backup repositories. So, it means that a newly created backup copy job won't re-create the whole backup chain. Instead, it will synthetically create one restore point containing the latest state of the chosen source.

However, if the forward incremental mode is used, you can manually copy those files to remote location and map a backup copy job to it afterwards. Starting from that moment, the backup copy job will keep adding increments to the chain.

Thanks.
cybava
Lurker
Posts: 2
Liked: never
Joined: Dec 03, 2014 9:00 am
Contact:

Re: How to copy all restore points in copy job ?

Post by cybava »

Thanks for your answer

No way for reverse incremental ?
veremin
Product Manager
Posts: 20415
Liked: 2302 times
Joined: Oct 26, 2012 3:28 pm
Full Name: Vladimir Eremin
Contact:

Re: How to copy all restore points in copy job ?

Post by veremin »

The backup copy job can be only mapped to forward incremental chain created either by backup or backup copy job. Thanks.