Moving jobs between backup hosts
Is there way currently, or with 5.0 coming, to easily move jobs between backup hosts without re-creating the jobs or starting from scratch?
For example: We have 3 physical hosts running Veeam to do backups. Each host currently has 5 jobs. On host 1, the jobs run long and overlap. On host 2, the jobs all get done very quickly. We would like to move a job from host 1 to host 2 to better "balance" the load.
For example: We have 3 physical hosts running Veeam to do backups. Each host currently has 5 jobs. On host 1, the jobs run long and overlap. On host 2, the jobs all get done very quickly. We would like to move a job from host 1 to host 2 to better "balance" the load.
-
- VP, Product Management
- Posts: 27357
- Liked: 2788 times
- Joined: Mar 30, 2009 9:13 am
- Full Name: Vitaliy Safarov
- Contact:
Re: Moving jobs between backup hosts
Hello Tim,
You may try moving Veeam configuration DB to another backup server. In this case all you will be able to split your jobs between two backup servers.
For more information, please have a look at the following topic:
http://www.veeam.com/forums/viewtopic.p ... 94&start=0
Hope it helps!
You may try moving Veeam configuration DB to another backup server. In this case all you will be able to split your jobs between two backup servers.
For more information, please have a look at the following topic:
http://www.veeam.com/forums/viewtopic.p ... 94&start=0
Hope it helps!
-
- Influencer
- Posts: 10
- Liked: never
- Joined: Dec 14, 2009 9:21 pm
- Full Name: Tim
Re: Moving jobs between backup hosts
My understanding is that this could only be done once. Since two servers are both already running and have different DBs, wouldn't this remove anything configured on the 2nd backup server?
Really, what we would like is a shared database so jobs can be moved between multiple backup hosts.
Really, what we would like is a shared database so jobs can be moved between multiple backup hosts.
-
- Chief Product Officer
- Posts: 31769
- Liked: 7271 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: Moving jobs between backup hosts
Hello Tim, adding such job management (move jobs between backup hosts) is on our roadmap. We plan to rely on our Enteprise Manager component to achieve this, since all backup hosts already have a connection established to it. Down the road, due to centralized management this functionality will also help to achieve additional useful capabilities like high availability for backup jobs (automatically moving jobs from failed backup host to another).
-
- Influencer
- Posts: 10
- Liked: never
- Joined: Dec 14, 2009 9:21 pm
- Full Name: Tim
Re: Moving jobs between backup hosts
Any idea when this might be coming? It is extremely difficult to manage even a reasonable sized install that is growing. Especially if using folders to automatically get new VMs backed up.
-
- Chief Product Officer
- Posts: 31769
- Liked: 7271 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: Moving jobs between backup hosts
We are currently planning this feature for the next major release after v5. This is a high priority feature for us.
-
- Enthusiast
- Posts: 87
- Liked: never
- Joined: Oct 20, 2009 2:49 pm
- Full Name: Joe Gremillion
- Contact:
Re: Moving jobs between backup hosts
Gostev,
That would a fantastic feature and really move your product into the enterprise realm. That would be a great help for us as well!
Keep up the good work!
That would a fantastic feature and really move your product into the enterprise realm. That would be a great help for us as well!
Keep up the good work!
-
- Novice
- Posts: 9
- Liked: 3 times
- Joined: Nov 06, 2009 4:35 pm
- Full Name: Neil Smith
- Contact:
Who is online
Users browsing this forum: Gostev, renatorichina, tkado, uk1984 and 117 guests