Retention Help...
All,
I need some assistance with the best way to achieve the retention policy i'm looking for. We do/keep a 30 day daily rotation and a monthly full that we retain for 2 years. What is the best way to achieve the intended retention?
Currently, saving 7 restore points on direct attached 3par san space (for fast restores) and set up backup copies to a B6500 HP StoreOnce array that is replicating to a duplicate StoreOnce in DR Datacenter. The backup copy is set to use GFS with 4 weekly and 24 Month Ends. It appears the backup copies are incremental copies only there doesn't appear to be a way to do GFS on regular backups. Thanks.
-Nick
I need some assistance with the best way to achieve the retention policy i'm looking for. We do/keep a 30 day daily rotation and a monthly full that we retain for 2 years. What is the best way to achieve the intended retention?
Currently, saving 7 restore points on direct attached 3par san space (for fast restores) and set up backup copies to a B6500 HP StoreOnce array that is replicating to a duplicate StoreOnce in DR Datacenter. The backup copy is set to use GFS with 4 weekly and 24 Month Ends. It appears the backup copies are incremental copies only there doesn't appear to be a way to do GFS on regular backups. Thanks.
-Nick
-
- Veeam Software
- Posts: 21138
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Retention Help...
Nick, you're doing everything right. There's no GFS retention in regular jobs and using backup copies is the way to go in your case.
-
- Expert
- Posts: 149
- Liked: 15 times
- Joined: Jan 02, 2015 7:12 pm
- Contact:
Re: Retention Help...
Any plans for GFS on regular, or full backups on the copies?
-Nick
-Nick
-
- Chief Product Officer
- Posts: 31804
- Liked: 7298 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: Retention Help...
Nick, an option to do Active Fulls in Backup Copy jobs, instead of them being forever-incremental, is planned for v9. Thanks!
-
- Expert
- Posts: 149
- Liked: 15 times
- Joined: Jan 02, 2015 7:12 pm
- Contact:
Re: Retention Help...
I suppose the simplest way to do this is create a vtl on the 6500 and run a 'tape' job and set retention for 2 years and replicate the vtl.
-
- Chief Product Officer
- Posts: 31804
- Liked: 7298 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: Retention Help...
This will work as well.