Hi.
Sometimes I get the request to make a last backup of a VM and save it for a number of months.
I was thinking about creating a backup job with and add the server to that - and run a backup.
Is far as I know the backup will not be deleted before the number of restore points have been reached.
When the retention period of the server is reached I just delete the backup on the disk.
Is this the best solution - or is there another way to do this.
If I get more servers to do the same with - can I just removed the first one from the job - and add the new one, and still keep the backup of the first one.
Clear?
Regards
Tore ML
-
- Expert
- Posts: 103
- Liked: 3 times
- Joined: Sep 13, 2017 11:12 am
- Full Name: Tore Mejlænder-Larsen
- Contact:
-
- Veteran
- Posts: 382
- Liked: 39 times
- Joined: Oct 17, 2013 10:02 am
- Full Name: Mark
- Location: UK
- Contact:
-
- Expert
- Posts: 103
- Liked: 3 times
- Joined: Sep 13, 2017 11:12 am
- Full Name: Tore Mejlænder-Larsen
- Contact:
Re: Save a final backup of a VM
Thanks.
Tore
Tore
Who is online
Users browsing this forum: acmeconsulting, d.artzen, gojain, Mildur, Semrush [Bot] and 122 guests