I read the FAQ on VMWare Proxy issues, not answering my question. The behavior I see is when I have a job that has say 10 VM's and I have specified 3 proxies, the job seems to only schedule one VM at a time and never uses the other 2 proxies. What am i missing, is there a setting? Should I not have 3 VM's backing up simultaneously frolm that job?
Thanks for any help
John
-
- Influencer
- Posts: 11
- Liked: never
- Joined: Aug 06, 2011 1:39 am
- Full Name: John Corbin
- Contact:
-
- Chief Product Officer
- Posts: 31803
- Liked: 7298 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: V6 Scheduling of VMs and Proxies
Hi John, no as within the job VMs are processed sequentially. If you have multiple jobs, they will be assigned to different proxies. Thanks!
-
- Influencer
- Posts: 11
- Liked: never
- Joined: Aug 06, 2011 1:39 am
- Full Name: John Corbin
- Contact:
Re: V6 Scheduling of VMs and Proxies
And to further clarify, multiple jobs will be assigned to a single proxy. I setup 6 jobs and assigned all of them to the same 3 proxies and the scheduler assigned two jobs per proxy. So I will have to use smaller # of VM's per job, more jobs, and possibly more proxies.....
thanks!
John
thanks!
John
Who is online
Users browsing this forum: Google [Bot] and 109 guests