Hi,
I need to restore an entire VM to a new ESXi host, while the restore is running, will the daily backup job still complete successfully? The original VM will not be touched in any way, the user just needs a copy of their VM to a new ESXi Host.
-
- Novice
- Posts: 3
- Liked: never
- Joined: Jul 24, 2020 1:54 pm
- Full Name: Nigel Debattista
- Contact:
-
- Veeam Software
- Posts: 2537
- Liked: 683 times
- Joined: Jun 14, 2013 9:30 am
- Full Name: Egor Yakovlev
- Location: Prague, Czech Republic
- Contact:
Re: will daily backup job still complete while restoring entire VM to new location
Hi Nigel,
Yes, new VM will have a new MoRefID and will be treated completely independent.
Source backup job will continue to work as before.
/Thanks!
Yes, new VM will have a new MoRefID and will be treated completely independent.
Source backup job will continue to work as before.
/Thanks!
-
- Novice
- Posts: 3
- Liked: never
- Joined: Jul 24, 2020 1:54 pm
- Full Name: Nigel Debattista
- Contact:
Re: will daily backup job still complete while restoring entire VM to new location
Hi Egor,
I don't think you understood my question, What I want to know is during the restore process, will the backup job continue to operate normally or will it fail to run until the restore is complete?
I don't think you understood my question, What I want to know is during the restore process, will the backup job continue to operate normally or will it fail to run until the restore is complete?
-
- Veeam Software
- Posts: 2537
- Liked: 683 times
- Joined: Jun 14, 2013 9:30 am
- Full Name: Egor Yakovlev
- Location: Prague, Czech Republic
- Contact:
Re: will daily backup job still complete while restoring entire VM to new location
That depends on backup chain mode. Forward incremental chain will process backup if restore is running in parallel.
Restore procedures also have highest priority for scheduling processing resources, for example free task slots will be allocated to restore job over backup job - in case of insufficient resources backup job will wait for resources to become available.
Restore procedures also have highest priority for scheduling processing resources, for example free task slots will be allocated to restore job over backup job - in case of insufficient resources backup job will wait for resources to become available.
-
- Novice
- Posts: 3
- Liked: never
- Joined: Jul 24, 2020 1:54 pm
- Full Name: Nigel Debattista
- Contact:
Re: will daily backup job still complete while restoring entire VM to new location
Hi Egor,
In fact, the job is set up as forward incremental, therefore the job should run even if the restore ha not completed if I understood correctly