Active/Synthetic Full at the same schedule

Post by MGT1981 » Apr 26, 2019 1:15 am

Hello,

I have what i hope is a very simple question. if i have a backup that is set to do a monthly Active full and a weekly Synthetic full on the same day of the week. During the week that the active full runs will the active full replace the synthetic or will both try to run?

HannesK
Veeam Software
Posts: 4021
Liked: 493 times
Joined: Sep 01, 2014 11:46 am
Location: Austria
Contact:

Re: Active/Synthetic Full at the same schedule

Post by HannesK » Apr 26, 2019 6:21 am 1 person likes this post

Hello,
it's a quite old answer from here
if you set both to active and synthetic full to happen on the same day, then only active full will happen.
I don't merge the topic because the old one was de-railed after some time...

Best regards,
Hannes

MGT1981
Influencer
Posts: 22
Liked: 2 times
Joined: Nov 21, 2014 12:30 am
Contact:

Re: Active/Synthetic Full at the same schedule

Post by MGT1981 » Apr 29, 2019 8:05 pm

thanks

Post Reply