Hello,
I have what i hope is a very simple question. if i have a backup that is set to do a monthly Active full and a weekly Synthetic full on the same day of the week. During the week that the active full runs will the active full replace the synthetic or will both try to run?
-
- Enthusiast
- Posts: 39
- Liked: 6 times
- Joined: Nov 21, 2014 12:30 am
-
- Product Manager
- Posts: 14840
- Liked: 3086 times
- Joined: Sep 01, 2014 11:46 am
- Full Name: Hannes Kasparick
- Location: Austria
- Contact:
Re: Active/Synthetic Full at the same schedule
Hello,
it's a quite old answer from here
Best regards,
Hannes
it's a quite old answer from here
I don't merge the topic because the old one was de-railed after some time...if you set both to active and synthetic full to happen on the same day, then only active full will happen.
Best regards,
Hannes
-
- Enthusiast
- Posts: 39
- Liked: 6 times
- Joined: Nov 21, 2014 12:30 am
Who is online