Host-based backup of VMware vSphere VMs.
Post Reply
t481
Enthusiast
Posts: 82
Liked: 1 time
Joined: Apr 28, 2015 7:52 am
Contact:

Backup Copy and Retention Question

Post by t481 »

Hi
I am trying to create a backup and backup copy jobs to achieve the following:

Backup daily incrementals on working days for 1 month
Weekly backups retained for 4 weeks
Monthly backups retained for 6 months


I created the following jobs:

Standard backup job:
- Daily incremental backups for 20 working days (1 month)
- Runs daily at 20.00

Backup Copy job
- Runs every 5 days
- Runs at 20.30 to capture the Friday backup
- Set to keep
- 4 x Weekly backups on Friday
- 6 x Monthly backups on the last Friday of the month.

Is the above correct to achieve the requirements?
Shestakov
Veteran
Posts: 7328
Liked: 781 times
Joined: May 21, 2014 11:03 am
Full Name: Nikita Shestakov
Location: Prague
Contact:

Re: Backup Copy and Retention Question

Post by Shestakov »

Hi, the settings look correct.
My only suggestion is to run backup copy daily, not once in 5 days.