Hi,
I've created a schedule for a job, which should make a backup every 6 months. But still it's making a backup every week. Maybe I'm overlooking something here?
So, schedule: Monthly at this time: 20:00 First Saturday Months: Selected January and July. If I look at the restore points, I have restore points on: 4 december, 11 december and 18 december.
Linked to the job is a backup copy to immutable, which has a GFS of keep weekly full backups for 1 week. Could this be causing this? I want 1 backup every 6 months and 1 Backup Copy which copies that backup to immu.
This is with B&R 11A.
Cheers,
Michael
-
- Enthusiast
- Posts: 45
- Liked: 6 times
- Joined: Apr 07, 2021 10:07 am
- Full Name: Michael Riesenbeck
- Contact:
-
- Veeam Software
- Posts: 540
- Liked: 193 times
- Joined: Mar 07, 2016 3:55 pm
- Full Name: Ronn Martin
- Contact:
Re: Configuring half year backups - scheduling
I certainly haven't tried this precise scenario but guessing you may still have weekly synthetic full's scheduled? Check the advanced settings in the storage selection dialog in the job wizard.
-
- Enthusiast
- Posts: 45
- Liked: 6 times
- Joined: Apr 07, 2021 10:07 am
- Full Name: Michael Riesenbeck
- Contact:
Re: Configuring half year backups - scheduling
Correct!
I've corrected it, so let's see what happens.
Cheers,
Michael
I've corrected it, so let's see what happens.