Copy interval has expired

Post by Danne84 »

We have an Exchange server thats 3TB+ and it takes a really long time to run the copy job.
So the jobs always ends with "Copy interval has expired"

Is it possible to change this interval time so the job can run longer?
foggy
Veeam Software
Posts: 21138
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Copy interval has expired

Post by foggy »

You can configure the copy interval in the job settings. Is it just the initial synchronization that cannot be completed or the initial sync is already done and incremental runs also take too long?
Danne84
Enthusiast
Posts: 56
Liked: never
Joined: May 12, 2014 2:05 pm
Contact:

Re: Copy interval has expired

Post by Danne84 »

"Copy interval has expired
Initial copy did not complete, and will resume on the next copy interval"

Ok so i can change the "Copy every 1 day" to 2 days for example and then it would run for 48hrs instead of 24 hrs?
foggy
Veeam Software
Posts: 21138
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Copy interval has expired

Post by foggy »

Have you used seeding for that VM?
Danne84
Enthusiast
Posts: 56
Liked: never
Joined: May 12, 2014 2:05 pm
Contact:

Re: Copy interval has expired

Post by Danne84 »

No i have not.
foggy
Veeam Software
Posts: 21138
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Copy interval has expired

Post by foggy »

Seeding backup copy job is a common practice in case of backing up considerably large VM. What kind of link do you have to remote location and what bottleneck stats are reported by the backup copy job?
Danne84
Enthusiast
Posts: 56
Liked: never
Joined: May 12, 2014 2:05 pm
Contact:

Re: Copy interval has expired

Post by Danne84 »

The copy jobs runs to USB-disks that we change every week.
Bottleneck is Source (QNAP NAS, 24 drives)
foggy
Veeam Software
Posts: 21138
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Copy interval has expired

Post by foggy »

Ah, so this is a local copy. In this case you have to increase the copy interval, indeed.
Danne84
Enthusiast
Posts: 56
Liked: never
Joined: May 12, 2014 2:05 pm
Contact:

Re: Copy interval has expired

Post by Danne84 »

Yes this is a local copy.
So increaseing the interval allows the job to run longer?
foggy
Veeam Software
Posts: 21138
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Copy interval has expired

Post by foggy »

Yes, it extends the time it allowed to copy the restore point data. What is the corresponding backup job schedule and how many restore points do you need to have on a rotated drive? If it is just a weekly full, then you can increase the interval to 7 days.
Danne84
Enthusiast
Posts: 56
Liked: never
Joined: May 12, 2014 2:05 pm
Contact:

Re: Copy interval has expired

Post by Danne84 »

We only have 2 restore points on the copy jobs, they run durring the weekend saturday-sunday.
And then we switch the USB-drives. And we are using "rotated hard drives" on the repository.
foggy
Veeam Software
Posts: 21138
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Copy interval has expired

Post by foggy »

Then longer interval should work for you.
chsu@iland.com
Lurker
Posts: 1
Liked: never
Joined: Jul 14, 2016 3:38 pm
Full Name: Charles
Contact:

Re: Copy interval has expired

Post by chsu@iland.com »

I have the similar issue where the time it was set to

Copy every 1 day starting at 5:00 AM
I start the job at 8:00 AM and around 5:00 AM it says

"Copy interval has expired
Initial copy did not complete, and will resume on the next copy interval"

the file is approximately 1.4 TB but it does not seem to finish. I just moved the time interval to

Copy every 30 day starting at 5:00 AM and still does not complete.

no restore points currently my other smaller jobs copy fine. Set retention to 5.

any suggestions?
foggy
Veeam Software
Posts: 21138
Liked: 2141 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Copy interval has expired

Post by foggy »

Charles, I guess, unless you click Sync Now, it first needs to complete the current copy interval and then start the new (longer) one.