Hello.
I configured an incremental backup job, on a Windows Share repository.
I have two jobs with two repositories.
The first Job performe a daily incremental backup and a full backup on sunday (tranform previous full backup into rollback). The second jobs has been configured with the same settings, but the fullbackup is never performed... I have only the first fullbackup.......
Have you got an idea about the problem ?
Thank you.
-
- Enthusiast
- Posts: 76
- Liked: 2 times
- Joined: May 22, 2012 12:09 pm
- Full Name: alex
- Contact:
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Job never do full backup
So the job was started on Sunday but did not perform a full backup? Could you please give us more details on both jobs settings (including scheduling)?
-
- VP, Product Management
- Posts: 27378
- Liked: 2800 times
- Joined: Mar 30, 2009 9:13 am
- Full Name: Vitaliy Safarov
- Contact:
Re: Job never do full backup
Seems like the second job missed it's configured schedule. The reason for that should be observed in the job session for that day. BTW, how many proxy servers do you have? And what is the max concurrent tasks value on them?leduke wrote:The second jobs has been configured with the same settings, but the fullbackup is never performed... I have only the first fullbackup.......
-
- Enthusiast
- Posts: 76
- Liked: 2 times
- Joined: May 22, 2012 12:09 pm
- Full Name: alex
- Contact:
Re: Job never do full backup
With your question, i checked one more time my jobs, and I found the problem:
The second Job was schedules after the first one, on the first one, the full backup was selected on Sunday, and also on the second job, but the first job withe the full backup finished on Monday at 01h00 on monday... So the second job started on monday so no full backup was selected on monday... I selected the full backup on monday for the second job and the week the full backup was performed...
It was a "schedule" mistake.
Your question give me the way to solve it.
Thank you
The second Job was schedules after the first one, on the first one, the full backup was selected on Sunday, and also on the second job, but the first job withe the full backup finished on Monday at 01h00 on monday... So the second job started on monday so no full backup was selected on monday... I selected the full backup on monday for the second job and the week the full backup was performed...
It was a "schedule" mistake.
Your question give me the way to solve it.
Thank you
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Job never do full backup
Dark side of the job chaining...