Hi
We have an incremental job set up to run every day from Monday to Saturday (included) + there is synthetic full set up to run on Saturday.
My question is - should I exclude incremental job from Saturday, as the syntetic full is running on that day?
Thanks
MAriusz
-
- Influencer
- Posts: 15
- Liked: never
- Joined: Jun 27, 2012 12:08 pm
- Full Name: Mariusz
- Contact:
-
- Veeam Software
- Posts: 21144
- Liked: 2143 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Synthetic full job query
Mariusz, actually you cannot do that. The synthetic full is created at the end of the regular job incremental run on the day it is scheduled at. Veeam B&R first creates an increment and then builds a new synthetic full based on the previous full and a chain of increments (Monday through Saturday, in your case). The increment created on Saturday is then deleted. If you exclude Saturday from the schedule, the job will still launch on that day and the synthetic full will be created.
-
- Influencer
- Posts: 15
- Liked: never
- Joined: Jun 27, 2012 12:08 pm
- Full Name: Mariusz
- Contact:
Re: Synthetic full job query
HI Foggy, thanks for your reply
SO I will leave the setting : incremental to run Monday to Saturday
Syntetic to run on Saturday.
SO I will leave the setting : incremental to run Monday to Saturday
Syntetic to run on Saturday.