Post by gcanales » Jan 29, 2014 8:41 pm

Hi,

I'm a little bit lost here, I'm upgrading from 6.5 to 7.0, but I want to keep using the machine where the 6.5 was deployed. I pretend to use it as a repository for the backup files and as a proxy, and Veeam 7 B&R server installed on a new machine.

On the brand new VBR 7 server I already configured the old 6.5 server as a repository and as a Proxy, and even asked me to "import backup jobs" on the GUI Wizard. But how I can use it those "imported jobs" to actually use them to continue backing the VMs on the new V7 deployed server and now use the old 6.5 server local storage just as the repository.

I've already tried to configure a new Job but I didn't see the option to keep using the imported jobs.

Any comments will be greatly appreciated :D

foggy
Veeam Software
Posts: 17715
Liked: 1481 times
Joined: Jul 11, 2011 10:22 am
Full Name: Alexander Fogelson
Contact:

Re: Upgrade and Import Jobs

Post by foggy » Jan 29, 2014 10:04 pm 1 person likes this post

Gilberto, you should just map your new jobs to the existing backup files. Thanks.

gcanales
Novice
Posts: 9
Liked: never
Joined: Feb 24, 2013 6:51 pm
Full Name: Gilberto Canales
Contact:

Re: Upgrade and Import Jobs

Post by gcanales » Jan 30, 2014 8:03 pm

Exactly what I was looking for, thanks a lot!