I have a VBR server with multiple jobs for 3 separate VMs that are approximately 12-14TB in size each. The jobs reference the vAPP that all 3 VMs are part of.

Question - when the first job runs it seems to lock the vAPP and the other 2 jobs wait on resources before kicking off. Is that expected behavior or is there a way to have all 3 jobs run at once without having to wait? The vAPP gets locked from what I can see.
-----------------------
Chris Childerhose
Veeam Vanguard / Veeam Legend / Veeam Ceritified Architect / VMCE
vExpert / VCAP-DCA / VCP8 / MCITP
Personal blog: https://just-virtualization.tech
Twitter: @cchilderhose
Alex Uryumtsev
Enthusiast
Posts: 51
Liked: 7 times
Joined: Oct 29, 2018 9:56 am
Full Name: Alexander Uryumtsev
Contact:

Re: vAPP Backup - Multiple VMs

Post by Alex Uryumtsev »

Hi Chris,

Have you enabled parallel processing in VBR console?

--au
chris.childerhose
Veeam Vanguard
Posts: 636
Liked: 154 times
Joined: Aug 13, 2014 6:03 pm
Full Name: Chris Childerhose
Location: Toronto, ON
Contact:

Re: vAPP Backup - Multiple VMs

Post by chris.childerhose »

Yes Parallel Processing is enabled in VBR. I think to get around this we are going to split the 3 VMs in to their own vAPP which we will then point each job to.
-----------------------
Chris Childerhose
Veeam Vanguard / Veeam Legend / Veeam Ceritified Architect / VMCE
vExpert / VCAP-DCA / VCP8 / MCITP
Personal blog: https://just-virtualization.tech
Twitter: @cchilderhose
Alex Uryumtsev
Enthusiast
Posts: 51
Liked: 7 times
Joined: Oct 29, 2018 9:56 am
Full Name: Alexander Uryumtsev
Contact:

Re: vAPP Backup - Multiple VMs

Post by Alex Uryumtsev »

Ok! What are you using, by the way, VMware vSphere or vCloud Director infrastructure?
chris.childerhose
Veeam Vanguard
Posts: 636
Liked: 154 times
Joined: Aug 13, 2014 6:03 pm
Full Name: Chris Childerhose
Location: Toronto, ON
Contact:

Re: vAPP Backup - Multiple VMs

Post by chris.childerhose »

We are using vCD as we are an MSP.
-----------------------
Chris Childerhose
Veeam Vanguard / Veeam Legend / Veeam Ceritified Architect / VMCE
vExpert / VCAP-DCA / VCP8 / MCITP
Personal blog: https://just-virtualization.tech
Twitter: @cchilderhose
Alex Uryumtsev
Enthusiast
Posts: 51
Liked: 7 times
Joined: Oct 29, 2018 9:56 am
Full Name: Alexander Uryumtsev
Contact:

Re: vAPP Backup - Multiple VMs

Post by Alex Uryumtsev »

I have a VBR server with multiple jobs for 3 separate VMs that are approximately 12-14TB in size each.
Why have you created separate jobs? Did you have special need for that?

You can have one job for 3 VMs, then VBR would process those vms in parallel.

Currently it is not possible to process vApp from multiple jobs. So it seems like a requirement update for the next version of the product, later I would keep vote for that.