I am confused about this. In the past when setting up backup jobs, I would go by restore points. So if I wanted 2 weeks retention (14 days) and I wanted to have the job run once a day (specified in the Schedule section), then I would have 14 restore points. If I want to run the job twice a day, I would have to have 28 restore points. So you can see the calculation would change depending on both the retention and the job frequency numbers specified.
Now, while creating a new job, I saw in the Storage tab that under Retention policy, I can choose either "restore points" or "days". If I choose days instead of restore points then go to Schedule and have the job run periodically every 2 hours, would Veeam do the math on the restore points for me, both now and in the future? This would make changing the retention a lot easier because I could always maintain 2 weeks retention while adjusting the job run frequency.
-
- Influencer
- Posts: 19
- Liked: 1 time
- Joined: Jun 26, 2019 7:27 pm
- Contact:
-
- Product Manager
- Posts: 20400
- Liked: 2298 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: question about backup job's retention policy restore points vs days (not having to calculate?)
Your understanding is correct:
Thanks!User Guide wrote:Keep restore points created during the last N days, where N is the specified number of days.