I setup a backup job for O365 with periodically run every 8 hours, under schedule I setup:
permitted from 11:00-11:59AM and 11:00-11:59PM, rest of the hours are denied.
I know from VBR that the job should be scheduled on the next free time slot but here I just have under next run <Not scheduled> and the job is not running and job is not running automatically.
Do you know please what I'm missing? I also started the job manually out the time slots, this was ok but as mentioned there is no other "next run".
Thank you!
-
- Service Provider
- Posts: 106
- Liked: 11 times
- Joined: Mar 20, 2018 6:31 am
- Full Name: Stano Sedliak
- Contact:
-
- Product Manager
- Posts: 9848
- Liked: 2607 times
- Joined: May 13, 2017 4:51 pm
- Full Name: Fabian K.
- Location: Switzerland
- Contact:
Re: VO365 job schedule periodically - not running
Hi Stano
The VB365 product doesn't work similar to VBR in that case.
If you have a disallowed time window at the start time of a job, then the job will do nothing and waits for the next scheduled start time. You must make sure, that the start time of a new interval lies in the allowed time window.
Seeing your allowed time window, do you require a 12 hourly backup job schedule?
Does the backup have to be 12AM /12PM or can it be after? Any reason, why the 8 hour stop doesn't work for your case?
Thanks
Fabian
The VB365 product doesn't work similar to VBR in that case.
If you have a disallowed time window at the start time of a job, then the job will do nothing and waits for the next scheduled start time. You must make sure, that the start time of a new interval lies in the allowed time window.
Seeing your allowed time window, do you require a 12 hourly backup job schedule?
Does the backup have to be 12AM /12PM or can it be after? Any reason, why the 8 hour stop doesn't work for your case?
Thanks
Fabian
Product Management Analyst @ Veeam Software