Host-based backup of VMware vSphere VMs.
Post Reply
jfmccue
Novice
Posts: 3
Liked: never
Joined: May 18, 2011 5:20 pm
Full Name: Jim McCue
Contact:

Merging two replication jobs?

Post by jfmccue »

I have two separate Veeam B&R 6.1 replication jobs, replicate_server_a and replicate_server_b over a WAN.

Is there a way to merge these two replicas into one job (i.e. replicate_server_a_and_b) without complete replication of one of the servers? I tried adding server_b to the server_a job, but it saw the current replication of server_b and wouldn't run. Just trying to consolidate some replication jobs so the scheduling is a bit simpler.

Thanks!

-Jim McCue
Rodey Law Firm
Gostev
Chief Product Officer
Posts: 31460
Liked: 6648 times
Joined: Jan 01, 2006 1:01 am
Location: Baar, Switzerland
Contact:

Re: Merging two replication jobs?

Post by Gostev »

Hi Jim, just add both VMs to the same job, and use the replica mapping functionality to avoid complete replication for the added VM. Obviously, you should also delete another job before starting the merged one. Thanks!