Hi
We have upgraded to Veeam 7 and all the jobs now have compression high as expected. We now plan to move all our vms to a new vcenter environment. From what I understand is that when we then re-add the vms from the new vcenter . This will automatically trigger a full backup of the vms. If we change the compression level to optimal at the same time we re-add the vms. Will this be enough to get benefits of the new compression in Veeam 7 to start working? Or do we have to explicit choose active full after we change compressions level to optimal?
\Masonit
-
- Service Provider
- Posts: 327
- Liked: 23 times
- Joined: Oct 09, 2012 2:30 pm
- Full Name: Maso
- Contact:
-
- Product Manager
- Posts: 20415
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: v7 changes in processing rate calculations
In fact, new active full isn’t required after changing compression level. Thanks.