Dear Veeam,

We are backuping our datacenter first local in the datacenter. Then with Copy Job to our location. And then to tape.
What we like to do, because after copy job, you need a scheduled job to do the backup.
Because the different time how long the copy job is busy, I need to schedule the backup 2 tape more then 3 hours later then it finish normal.

Kind regards,

Daag van der Meer
Hitachi PowerTools
Dima P.
Product Manager
Posts: 14417
Liked: 1576 times
Joined: Feb 04, 2013 2:07 pm
Full Name: Dmitry Popov
Location: Prague
Contact:

Re: [Feature Request] Copy Job to tape Job

Post by Dima P. »

Hello dvandermeer.

Can you please clarify the request? Looks like you want to either start tape job right after copy job, is that correct? Thanks.
dvandermeer
Novice
Posts: 6
Liked: never
Joined: Jun 15, 2018 7:04 am
Full Name: Daag van der Meer
Contact:

Re: [Feature Request] Copy Job to tape Job

Post by dvandermeer »

Thats right.
Like a normal backup to disk, there you can run a job to tape when finished.
pkelly_sts
Veteran
Posts: 600
Liked: 66 times
Joined: Jun 13, 2013 10:08 am
Full Name: Paul Kelly
Contact:

Re: [Feature Request] Copy Job to tape Job

Post by pkelly_sts »

I'm sure I asked for something similar but the basic response was, a copy job is an "always running" task so it never ends as such, so can't trigger another job after it "completes" because it'll always still be running (waiting).
veremin
Product Manager
Posts: 20284
Liked: 2258 times
Joined: Oct 26, 2012 3:28 pm
Full Name: Vladimir Eremin
Contact:

Re: [Feature Request] Copy Job to tape Job

Post by veremin »

Just to be more precise - backup copy job actually can trigger post-job activity. But it does so once the synchronization interval expires. Thanks.
pkelly_sts
Veteran
Posts: 600
Liked: 66 times
Joined: Jun 13, 2013 10:08 am
Full Name: Paul Kelly
Contact:

Re: [Feature Request] Copy Job to tape Job

Post by pkelly_sts »

Ah, understood, but still wouldn't really help in the scenario here. Heck I'd add my vote to a "post sync task" feature request.
veremin
Product Manager
Posts: 20284
Liked: 2258 times
Joined: Oct 26, 2012 3:28 pm
Full Name: Vladimir Eremin
Contact:

Re: [Feature Request] Copy Job to tape Job

Post by veremin »

Like a normal backup to disk, there you can run a job to tape when finished.
If backup to tape job is meant here, can you tell me why "as backup files appear" schedule option does not work for you? Thanks.
pkelly_sts
Veteran
Posts: 600
Liked: 66 times
Joined: Jun 13, 2013 10:08 am
Full Name: Paul Kelly
Contact:

Re: [Feature Request] Copy Job to tape Job

Post by pkelly_sts »

Not sure who your question was aimed at but from my perspective I wasn't actually aware of that option (is it a recent addition?) but even if I was, I think the I/O hit would be pretty bad if I was doing per-VM backups and VM1 was being spooled to tape from the same storage as VM2 is being written to the same spindles?

To be fair, this is another good scenario/argument for a small-ish SSD storage as first-level backups as it shouldn't suffer from such issues.
Post Reply

Who is online

Users browsing this forum: No registered users and 9 guests