Discussions related to exporting backups to tape and backing up directly to tape.
Post Reply
leithm
Service Provider
Posts: 14
Liked: 1 time
Joined: May 19, 2016 12:52 am
Full Name: Leith Magon
Contact:

GFS Schedule and VBK Map ID 01974454

Post by leithm »

Hi all,

I've spoken with support on this one but wasn't really able to get anywhere so putting it out to the community.

I've got a job backing up some file servers to disk that runs at 12:05am each day. It takes between 3-4hrs. Then I have a GFS schedule doing Weekly / Monthly backups to tape of this job.

This is the output I would normally get..

Image


Occasionally this is happening.. (too frequently, results in the job spanning longer than the 24hr window before the disk job kicks off again)

Attempts to run at the scheduled time.. fails..

Image


Then runs again once the disk backup has completed but it now decides its going to use a vbk map resulting in large backup file (twice the usual backup size) + twice the copy time

Image


This all may be expected behavior in which case please explain to me how I can

1. Run a GFS job using reverse incremental backups without the above failing behavior occurring
2. Stop a disk job cancelling a tape job

Many thanks for any insights here
Dima P.
Product Manager
Posts: 14720
Liked: 1705 times
Joined: Feb 04, 2013 2:07 pm
Full Name: Dmitry Popov
Location: Prague
Contact:

Re: GFS Schedule and VBK Map ID 01974454

Post by Dima P. »

Hi leithm,

May I suggest to upgrade your VBR to latest v9.5? Firstly, most of the issues with GFS were fixed in this version. Secondly, there is an option to Prevent tape job from being interrupted by primary source backup job which may solve your case.
Post Reply

Who is online