Hi,
i was wondering why my tape job created a new meda set even so the "on these day" is not checked for the day :
My goal is to get a media set (that starts on the thursday) and will eventually be done by satursday / sunday.
so in my pool i will see only :
Media set Thursday 27 February
Media set Thursday 5 March
Media set Thursday 12 March
Media set Thursday 19 March
etc ...
Thank for your help !
-
- Lurker
- Posts: 2
- Liked: never
- Joined: Feb 28, 2020 2:13 pm
- Contact:
Re: Media set
i looked at the doc : https://helpcenter.veeam.com/archive/ba ... _sets.html
In some cases, Veeam forcibly starts a new media set, even if media pool settings do not instruct Veeam to do so. It happens when a job starts, but the tape that was planned for writing data cannot be used. In this situation, Veeam takes a new tape, and starts a new media set on it. For example, the situation may be as following:
The required tape is offline. If you bring such tape online before the tape job starts, it will be used as planned.
If the media pool is scheduled to export tapes. Exporting closes the current media set and starts a new one on the next job run.
The required tape is hardware or software protected.
In library failover on the following events: library is offline and all drives are busy. When a tape library is failed over on these events, Veeam Backup & Replication starts a new media set even if the global media pools are configured to always continue one media set.
Note that if a new media set is started, scheduled or forced, the previous media set cannot be resumed.
how can i prevent this to happen ?
thanks !
In some cases, Veeam forcibly starts a new media set, even if media pool settings do not instruct Veeam to do so. It happens when a job starts, but the tape that was planned for writing data cannot be used. In this situation, Veeam takes a new tape, and starts a new media set on it. For example, the situation may be as following:
The required tape is offline. If you bring such tape online before the tape job starts, it will be used as planned.
If the media pool is scheduled to export tapes. Exporting closes the current media set and starts a new one on the next job run.
The required tape is hardware or software protected.
In library failover on the following events: library is offline and all drives are busy. When a tape library is failed over on these events, Veeam Backup & Replication starts a new media set even if the global media pools are configured to always continue one media set.
Note that if a new media set is started, scheduled or forced, the previous media set cannot be resumed.
how can i prevent this to happen ?
thanks !
-
- Product Manager
- Posts: 20415
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Media set
Make sure that none of the described situation happens. Besides that there is no specific settings that control it. Thanks!
-
- Expert
- Posts: 115
- Liked: 15 times
- Joined: Sep 05, 2016 5:08 am
- Full Name: Nathan Oldfield
- Contact:
Re: Media set
When is your next job scheduled to run using that media pool after 6.30pm on Thursday?