Backup Copy Job Schedule
Hi All,
We are still in the process of finalising the design of our Veeam environment and looking at the options for holding our retentions. First I will explain our current setup:
We have approx. 200VMs (35TB) in one vCenter cluster and do a Veeam replication to another site for DR - Working Well.
We are also backing up to local storage using reverse incremental every night keeping 4 weeks - Working Well.
I have a secondary location with disk available for saving the retentions, currently we are running a backup copy job continuously for a small amount of the backups for testing. However I would prefer to not be copying data everyday just once a week, would this be possible or recommended with the backup copy jobs?
For an example of keeping a 6 month retention, I was thinking we could use these settings
Copy Every: 1 Day at 9PM
Restore Points to keep: 2
Keep Restore points for archival purposes: 6 monthly (First Saturday)
Change the schedule to only transfer from 9PM Friday to Sunday night.
Would this work or is there a better way to set this up? I don't need the data copied to the retentions location immediately as I have a DR site for this.
Thanks
We are still in the process of finalising the design of our Veeam environment and looking at the options for holding our retentions. First I will explain our current setup:
We have approx. 200VMs (35TB) in one vCenter cluster and do a Veeam replication to another site for DR - Working Well.
We are also backing up to local storage using reverse incremental every night keeping 4 weeks - Working Well.
I have a secondary location with disk available for saving the retentions, currently we are running a backup copy job continuously for a small amount of the backups for testing. However I would prefer to not be copying data everyday just once a week, would this be possible or recommended with the backup copy jobs?
For an example of keeping a 6 month retention, I was thinking we could use these settings
Copy Every: 1 Day at 9PM
Restore Points to keep: 2
Keep Restore points for archival purposes: 6 monthly (First Saturday)
Change the schedule to only transfer from 9PM Friday to Sunday night.
Would this work or is there a better way to set this up? I don't need the data copied to the retentions location immediately as I have a DR site for this.
Thanks
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Backup Copy Job Schedule
Paul, with the "Copy every" interval set to 1 day backup copy job will try to copy changes every day, but will fail each time except the allowed Friday night. You'd better set the "Copy every" interval to 1 week to meet your requirements. Thanks.
-
- Novice
- Posts: 8
- Liked: never
- Joined: Apr 16, 2014 10:52 am
- Full Name: Paul Wilson
- Contact:
Re: Backup Copy Job Schedule
Thanks for the reply, so I would change the "copy every" interval to 7 Day? How can we make sure it runs on a Friday night?
Sorry anther questions, if we then set our retentions to Keep on a Monday, will the transform run on a Monday to does it wait until another copy job process has started?
Sorry anther questions, if we then set our retentions to Keep on a Monday, will the transform run on a Monday to does it wait until another copy job process has started?
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Backup Copy Job Schedule
Yes, you can change the setting to 7 days and start new synchronization interval by selecting the Sync Now command on the job's shortcut menu at the required time (on Friday).palw wrote:Thanks for the reply, so I would change the "copy every" interval to 7 Day? How can we make sure it runs on a Friday night?
Not sure I fully understand the question. Could you please clarify it a little further?palw wrote:Sorry anther questions, if we then set our retentions to Keep on a Monday, will the transform run on a Monday to does it wait until another copy job process has started?
-
- Product Manager
- Posts: 20413
- Liked: 2301 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Backup Copy Job Schedule
1)You can also start new synchronization interval automatically. Just schedule this custom PS script to run Friday.
2) Are you talking here about GFS rotation scheme ("Keep the following restore points for archival purpose")? If so, then, the backup copy job won't run GFS transform on Monday, instead, it will wait until the oldest restore point (.vbk) reaches the given day, and only then backup copy job will perform it.
Thanks.
2) Are you talking here about GFS rotation scheme ("Keep the following restore points for archival purpose")? If so, then, the backup copy job won't run GFS transform on Monday, instead, it will wait until the oldest restore point (.vbk) reaches the given day, and only then backup copy job will perform it.
Thanks.