Backup Defragment/Compact Schedule

Availability for the Always-On Enterprise

Backup Defragment/Compact Schedule

Veeam Logoby rjlewis » Tue Jan 03, 2017 12:07 am

Using VB&R 9.5

I have a backup job configured with forever forward incremental backup which is scheduled to run daily at 12:30AM. A synthetic full is included for Saturday. The backup job is also configured to perform the maintenance tasks defragment and compact on first Sunday of the month, and the health check on the second Sunday of the month. I chose Sunday because it is a quiet day with no tape copies being produced - at least on those first 2 weekends of the month.

Today (3/1/17), I was wondering why the backup to tape run had not completed (which follows the daily disk backup Tuesday-Saturday AM), and discovered that the compacting of the full backup was running today instead of on Sunday (1/1/17).

Why didn't the compaction task run on Sunday?
rjlewis
Novice
 
Posts: 4
Liked: never
Joined: Thu Oct 27, 2016 12:07 am
Full Name: Richard Lewis

Re: Backup Defragment/Compact Schedule

Veeam Logoby Mike Resseler » Tue Jan 03, 2017 5:42 am

Richard,

Hard to tell why it didn't run. Without logs it will be difficult to figure out what is going on and why did it run on Tuesday (did it start on Sunday or only started on Tuesday?)

I would look a little bit more into the History tab of the UI and see what exactly has happened. If it is completely wrong and not per your settings, I would log a support call so that our engineers can dive deeper in the logs to figure out what is happening

Mike
Mike Resseler
Veeam Software
 
Posts: 3381
Liked: 384 times
Joined: Fri Feb 08, 2013 3:08 pm
Location: Belgium, the land of the fries, the beer, the chocolate and the diamonds...
Full Name: Mike Resseler


Return to Veeam Backup & Replication



Who is online