Hello Community
We are using vSphre 4.1 u2date with 2x ESX 4.1i u2date.
We have Veeam Backup and Repl 5.0.2
The needing is to do a snapshot of each VM in a seperat job. The Storage is a Nas with cifs.
We need 7 Restore Points.
2 Moth ago i set the
Restorepoints to keep on disk: 7
Delete VMs retention period: 7
I have set in the advanced settings:
Incremental
but i havent enabled the syntethic and also not the transform.
So....
The Job does a full backup at the beginng and after that only inc's. (*.vib)
Well now the Sotrage is filled over 90% and it seams that the older (*.vib) of the VM's would not be deleted.
So i set yesterday night the Enable syntetic fulls (forever-Inc) and also Transform previious full into rollbacks.
Some of the vm's are still dooing the syntetc (cause the lots of (*.vib) files.
It seams that the Veeam now taking the *.vib and convert this into *.vrb files and then update the *.vbk.
Settings:
Settings2:
Butt one of the 15 Vm's is finished. If im looking now in the Cifs share there are more than 7 *.vrb's .....
but i set the option Restorepoints to keep on disk: 7
Where i have donne the mistake?
Thanks for yor fast anserws.
Kind Regards
Florian
We are using vSphre 4.1 u2date with 2x ESX 4.1i u2date.
We have Veeam Backup and Repl 5.0.2
The needing is to do a snapshot of each VM in a seperat job. The Storage is a Nas with cifs.
We need 7 Restore Points.
2 Moth ago i set the
Restorepoints to keep on disk: 7
Delete VMs retention period: 7
I have set in the advanced settings:
Incremental
but i havent enabled the syntethic and also not the transform.
So....
The Job does a full backup at the beginng and after that only inc's. (*.vib)
Well now the Sotrage is filled over 90% and it seams that the older (*.vib) of the VM's would not be deleted.
So i set yesterday night the Enable syntetic fulls (forever-Inc) and also Transform previious full into rollbacks.
Some of the vm's are still dooing the syntetc (cause the lots of (*.vib) files.
It seams that the Veeam now taking the *.vib and convert this into *.vrb files and then update the *.vbk.
Settings:
Settings2:
Butt one of the 15 Vm's is finished. If im looking now in the Cifs share there are more than 7 *.vrb's .....
but i set the option Restorepoints to keep on disk: 7
Where i have donne the mistake?
Thanks for yor fast anserws.
Kind Regards
Florian
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Newbee Qestion to Backup Restore Points
Florian, its easy to explain why did you have more restore points while using incremental mode. We have a bunch of existing threads covering Veeam B&R behavior in this case. Please look at this one, for example.
I would assume that after switching to reverse incremental mode you have more than 7 vrb files according to the Deleted VMs retention period setting (see this topic for more information). But according to you, you have only one VM per job (is that right?) and in this case you should definitely have only 7 vrb files for each of them. Could you please start the restore wizard for that VM and see how much restore points are available there? It could be that you have corrupt backup chain due to some reason (Veeam B&R could not delete one of the vrb files due to connection problem, for example). You should not have more than 7 restore points available in the wizard.
Thanks.
I would assume that after switching to reverse incremental mode you have more than 7 vrb files according to the Deleted VMs retention period setting (see this topic for more information). But according to you, you have only one VM per job (is that right?) and in this case you should definitely have only 7 vrb files for each of them. Could you please start the restore wizard for that VM and see how much restore points are available there? It could be that you have corrupt backup chain due to some reason (Veeam B&R could not delete one of the vrb files due to connection problem, for example). You should not have more than 7 restore points available in the wizard.
Thanks.
-
- Novice
- Posts: 6
- Liked: never
- Joined: Nov 25, 2011 7:30 am
- Full Name: Florian Shcmutz
- Contact:
Re: Newbee Qestion to Backup Restore Points
Hi foggy
Thanks for your feedback.
Yes i have only one vm per Job.
In The Recovery mode i see entries according to the vrb files. So i have entries since aug.
Hehe sorry i should say that the upper 2 pictures are the same server. and thats only the start and the end between the viewable restore Points on the printscreen are many more XD
Thanks for your feedback.
Yes i have only one vm per Job.
In The Recovery mode i see entries according to the vrb files. So i have entries since aug.
Hehe sorry i should say that the upper 2 pictures are the same server. and thats only the start and the end between the viewable restore Points on the printscreen are many more XD
-
- Novice
- Posts: 6
- Liked: never
- Joined: Nov 25, 2011 7:30 am
- Full Name: Florian Shcmutz
- Contact:
Re: Newbee Qestion to Backup Restore Points
And the Report to the Server witch are done the Transform last night.
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Newbee Qestion to Backup Restore Points
It seems like something went wrong after your switch to reverse incremental - restore points are not deleted for some reason. I would recommend to proceed with our support team on this as they manage to investigate this issue faster via logs or webex session. Thanks.
-
- Novice
- Posts: 6
- Liked: never
- Joined: Nov 25, 2011 7:30 am
- Full Name: Florian Shcmutz
- Contact:
Re: Newbee Qestion to Backup Restore Points
Oky thanks
I see one of the servers has done the job correctly.
I will wait till all servers hans finished the syntethic and try the faild one's again. (seperatly)
If its not helping i will open a case on Monday.
Thanks for your replys.
Kind Regards
Sanktis
I see one of the servers has done the job correctly.
I will wait till all servers hans finished the syntethic and try the faild one's again. (seperatly)
If its not helping i will open a case on Monday.
Thanks for your replys.
Kind Regards
Sanktis
-
- Novice
- Posts: 6
- Liked: never
- Joined: Nov 25, 2011 7:30 am
- Full Name: Florian Shcmutz
- Contact:
Re: Newbee Qestion to Backup Restore Points
Hmm okee
the most of the jobs are running and does the syntehtic backup correctly.
But some are still not finished.
I have to reboot the backup server many times. caus.......
Its a DL380G7 with one CPU 6 Cores and 12 GB Ram
The problem is now that it seams taht the veeam backup jobs leeking memory.
if the job starts all is oke.. after 2 or 3 houres the mem of 12 gb is consumed completly.
The jobs in the taskmanager consumes never that size of memory they are all something around 100'000 K.
Any issu known with this? The CPU is not realy used over all cores 50 % (with an active snapshot backupjob (Not Syntethic)) The Synthetic Backups consumed around 5 - 10 % CPU not more. The Network is also not realy on load during the syntetc only phases.
Well my prob is that i have no around 1.5 - 2 TB Data witch i have to change from incremetel -> Syntetci 7 Restore Points... and i cant finish the jobs till the mem leek is filling up my mem ^^
Any Sugesstions? XD
Kind Regards
Florian
the most of the jobs are running and does the syntehtic backup correctly.
But some are still not finished.
I have to reboot the backup server many times. caus.......
Its a DL380G7 with one CPU 6 Cores and 12 GB Ram
The problem is now that it seams taht the veeam backup jobs leeking memory.
if the job starts all is oke.. after 2 or 3 houres the mem of 12 gb is consumed completly.
The jobs in the taskmanager consumes never that size of memory they are all something around 100'000 K.
Any issu known with this? The CPU is not realy used over all cores 50 % (with an active snapshot backupjob (Not Syntethic)) The Synthetic Backups consumed around 5 - 10 % CPU not more. The Network is also not realy on load during the syntetc only phases.
Well my prob is that i have no around 1.5 - 2 TB Data witch i have to change from incremetel -> Syntetci 7 Restore Points... and i cant finish the jobs till the mem leek is filling up my mem ^^
Any Sugesstions? XD
Kind Regards
Florian
-
- Chief Product Officer
- Posts: 31814
- Liked: 7302 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: Newbee Qestion to Backup Restore Points
All your memory goes into the system cache > Memory performance