Hi,
We are reviewing a DR scenario with Veeam and were wondering if there is an option to halt any retention policies from processing during a DR situation where every backup version might be crucial. (Such DRs can take a while as usually the first focus is the most mission critical servers and then slowly all other servers are brought back).
-
- Influencer
- Posts: 22
- Liked: 2 times
- Joined: Feb 06, 2023 7:22 pm
- Contact:
-
- Chief Product Officer
- Posts: 31806
- Liked: 7300 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: Pause retention during DR situation
Hello, currently removing backup from configuration should achieve this. And thanks for sharing your scenario, we will look at adding such capability ASAP. Thanks!
-
- Influencer
- Posts: 22
- Liked: 2 times
- Joined: Feb 06, 2023 7:22 pm
- Contact:
Re: Pause retention during DR situation
Doesn't removing backups from config prevent using them for restores until they are reimported in which case retention processing restarts?
-
- Chief Product Officer
- Posts: 31806
- Liked: 7300 times
- Joined: Jan 01, 2006 1:01 am
- Location: Baar, Switzerland
- Contact:
Re: Pause retention during DR situation
No, retention does not apply to imported backups.