I have a job with a secondary copy to tape that is scheduled to run once a month. However, it appears to be running a daily full backup. I assume this is because that on the backup tab of Storage>Advanced, my predecessor set the job for periodic synth fulls as well as periodic fulls 7 days a week. This doesn't really make sense to me since the job is, as I said, scheduled to run only on the last Wednesday of the month, but there you have it.
Has anyone seen this behavior before and will removing/changing those settings resolve the nightly full problem?
-
- Lurker
- Posts: 1
- Liked: never
- Joined: Oct 14, 2015 2:03 pm
- Full Name: Hank Hill
- Contact:
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Schedule strangeness
Hank, you're correct, the behavior is the result of having synthetic fulls scheduled every day (synthetic fulls are performed regardless of the job main schedule).