I want to do incrementals Mon, Tue, Wed and Thu, then schedule an Active Full Backup on Friday. When setting up the job under Storage --> Advanced, I set the full backup to run on Fridays:

Now, when I get to the schedule page do I also need to select Friday as well? Or will the job know to run the Active Full on that day already?

My logic is that if I select Friday in the schedule the job will run another incremental, followed by the active full backup. I guess I can just let it run through this Saturday and see what it does, but just thought I would ask. Thanks!