Hi all,

I have a job to backup two file servers, totalling 4TB approx. Job configuration:
Direct SAN Access
Reverse Incremental
Optimal compression
Storage target LAN optimised
Change Block Tracking

We're backing up to a QNAP NAS.

This job regularly takes over 24hrs. We DoubleTake this server to our data center for additional resilience. Could DoubleTake cause this job to take a long time?


Thanks
Vitaliy S.
VP, Product Management
Posts: 27377
Liked: 2802 times
Joined: Mar 30, 2009 9:13 am
Full Name: Vitaliy Safarov
Contact:

Re: Backing up large VM

Post by Vitaliy S. »

It's hard to say what is causing it without further details. Could you please tell what is the processing rate for this two VMs? And what is the usual VRB file size for this job?
chg_it
Influencer
Posts: 21
Liked: never
Joined: Jun 08, 2010 2:07 pm
Full Name: IT Department
Contact:

Re: Backing up large VM

Post by chg_it »

Hi there,

I've been tweaking backups and I'm getting a better rate now. It seems that slow backups are sporadic.

I'm going to put this down to network for now and investigate internally.

Many thanks
Vitaliy S.
VP, Product Management
Posts: 27377
Liked: 2802 times
Joined: Mar 30, 2009 9:13 am
Full Name: Vitaliy Safarov
Contact:

Re: Backing up large VM

Post by Vitaliy S. »

Ok, please let us know if you need any assistance.

On top of that, you may want to use forums search to look for similar problems and common troubleshooting steps > http://www.veeam.com/forums/search.php? ... rmance+san