Comprehensive data protection for all workloads
Post Reply
topry
Enthusiast
Posts: 49
Liked: 1 time
Joined: Jan 07, 2011 9:30 pm
Full Name: Tim O'Pry
Contact:

Start periodic jobs other than top of hour

Post by topry »

We are using the periodic schedule, setting varying hours throughout the week to run a job, avoiding peak usage periods. To prevent overlap with other jobs, we would like to set the periodic job to start at :30 after the hour, but have not found a way to do this.

Is it possible to schedule a periodic job that runs once an hour but starts at a set number of minutes after the top of the hour?
Gostev
Chief Product Officer
Posts: 31561
Liked: 6724 times
Joined: Jan 01, 2006 1:01 am
Location: Baar, Switzerland
Contact:

Re: Start periodic jobs other than top of hour

Post by Gostev »

Not possible with v5, and should not be needed with v6, since it manages job concurrency automatically for you.