Agent-based backup of Windows, Linux, Max, AIX and Solaris machines.
Post Reply
mirfan
Enthusiast
Posts: 40
Liked: never
Joined: Dec 17, 2020 7:28 am
Contact:

backup jobs configuration

Post by mirfan »

Hi,

I want to asked about backup job.
whether I have to using "enable application-aware processing" for SAP application server?

should I using pre-freeze and post-thaw too?

Regards
Dima P.
Product Manager
Posts: 14417
Liked: 1576 times
Joined: Feb 04, 2013 2:07 pm
Full Name: Dmitry Popov
Location: Prague
Contact:

Re: backup jobs configuration

Post by Dima P. »

Hello mirfan,

Application-aware processing will allow you to use pre/post freeze scripts along with the image-level backup of virtual machine, good overview of possible options from the best practice guide. In addition to that I'd recommend to check the Veeam Plug-in for SAP HANA as that might be quite handy when we talk about application processing. Very detailed blog post series 3 steps to protect your SAP HANA database if you are interested. Cheers!
mirfan
Enthusiast
Posts: 40
Liked: never
Joined: Dec 17, 2020 7:28 am
Contact:

Re: backup jobs configuration

Post by mirfan »

Hi Dima

Thanks for reply.
I have check in the veeam documentation pre/post freeze is used only with hana database server. CMIIW
just want to make sure there is no need pre/post freeze script on the SAP applicaton server.

Thanks
PetrM
Veeam Software
Posts: 3263
Liked: 528 times
Joined: Aug 28, 2013 8:23 am
Full Name: Petr Makarov
Location: Prague, Czech Republic
Contact:

Re: backup jobs configuration

Post by PetrM »

Hello,

Could you please clarify which database are you running on the server you're going to back up?

Probably, it would make sense to leverage the pre-freeze and post-thaw scripts in order to stop the SAP system before backup and start it once the job is completed. At least it is one of prerequisites mentioned in this article.

Thanks!
mirfan
Enthusiast
Posts: 40
Liked: never
Joined: Dec 17, 2020 7:28 am
Contact:

Re: backup jobs configuration

Post by mirfan »

Hi,

we have
- SAP server application
- SAP server with Hana database
- SAP server with sybase

as I know pre-freeze and post-thaw are used for servers that use the hana database.
is it any pre-freeze and post-thaw for SAP application server and SAP server with sybase? please share

Thanks
PetrM
Veeam Software
Posts: 3263
Liked: 528 times
Joined: Aug 28, 2013 8:23 am
Full Name: Petr Makarov
Location: Prague, Czech Republic
Contact:

Re: backup jobs configuration

Post by PetrM » 1 person likes this post

I have no examples of scripts for SAP server or Sybase but the basic idea is to bring application data into consistent state prior backup. I guess that "quiesce database" command should be used in the scripts for Sybase and "release" tag should be specified in the post-thaw script to resume database activity.

Thanks!
mirfan
Enthusiast
Posts: 40
Liked: never
Joined: Dec 17, 2020 7:28 am
Contact:

Re: backup jobs configuration

Post by mirfan »

Hi Petr,

I have create using quiesce database hold and release.
but have not try it yet.

Thanks
Post Reply

Who is online

Users browsing this forum: No registered users and 6 guests