Veeam Logoby Sarek70 » Sun Jun 19, 2016 2:37 am

I make a incremental backup on weekdays. On Saturday create a full backup and transform the incremental files (vib) to reverse incremental files (vrb). At 12:00:00 AM on Sunday the full backup should be moved to tape. But when i look at the job it is still pending. In the detail screen i see the following message:

Code: Select all
No restore points found for the set date. Synthesized full backup was not created because the most recent restore point is a full backup Backup NfsVol12016-06-18T203035.vbk (6/18/2016 8:30:35 PM)

Question 1Why is the weekly tape job (made in GFS media pool) not moving the full backup to tape? and why is it asking for a Synthesized full backup ?

Question 2 Why can't i schedule the start of the tape job in a GFS pool, it automatically sets the time at 12:00:00am? I want to set it to a later time cause a second backup job is still transforming the vib files to vrb files at that time
Sarek70
Novice
 
Posts: 9
Liked: never
Joined: Wed Apr 22, 2015 11:41 am

Re: First GFS backup

Veeam Logoby Shestakov » Sun Jun 19, 2016 10:59 am

Sarek70 wrote: But when i look at the job it is still pending. In the detail screen i see the following message:

Do you mean backup or tape-backup job?

Sarek70 wrote:Question 2 Why can't i schedule the start of the tape job in a GFS pool, it automatically sets the time at 12:00:00am? I want to set it to a later time cause a second backup job is still transforming the vib files to vrb files at that time

Please refer to a related discussion. Thanks!
Shestakov
Veeam Software
 
Posts: 4856
Liked: 394 times
Joined: Wed May 21, 2014 11:03 am
Location: Saint Petersburg
Full Name: Nikita Shestakov


Return to Tape



Who is online

Users browsing this forum: No registered users and 4 guests