I have a backup schedule for "FILES to tape" like so:
Monday AM - Full, Weekend Pool
Tuesday AM - Inc, Weekday Pool
Wednesday AM - Inc, Weekday Pool
Thursday AM - Inc, Weekday Pool
Friday AM - Inc, Weekday Pool
Saturday AM - Inc, Weekday Pool
This Monday AM, I added an additional folder to the "FILES to tape" job before it ran the Full backup. The full backup started and pulled the correct tape in the Weekend Pool. The job ran forever and hung because the folder I added was a folder with thousands of small files, which I know VEEAM currently is very slow at backing up. Rather than wait 3 weeks for the job to finish, I cancelled the job, edited it to remove the folder I had added, and then restarted the job. When I did this, it pulled the Weekday Pool tape from the Friday a few days ago (rather than the tape it had just been writing to out of the Weekend Pool) and ran what looks like another incremental to that instead of continuing the full which I had to cancel.
Is that expected behavior or can anyone give me an idea what might have happened?
-
- Veteran
- Posts: 338
- Liked: 35 times
- Joined: Jan 20, 2012 2:36 pm
- Full Name: Christensen Farms
- Contact:
-
- Product Manager
- Posts: 20413
- Liked: 2301 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Full Backup Cancel and then re-runs as Weekday Increment
Hi, Christensen, have you tried to erase the given tape medium before starting the file to tape job from the scratch? Probably, some files were written to tape medium and VB&R decided that successful full run was performed, and started copying incremental files, using corresponding Media Pool ("Weekday") and the oldest weekday tape.
From my perspective, the erase operation should remove the information regarding full run from the backup console and you should be able to copy desired files to the correct cassettes.
Thanks.
From my perspective, the erase operation should remove the information regarding full run from the backup console and you should be able to copy desired files to the correct cassettes.
Thanks.
-
- Veteran
- Posts: 338
- Liked: 35 times
- Joined: Jan 20, 2012 2:36 pm
- Full Name: Christensen Farms
- Contact:
Re: Full Backup Cancel and then re-runs as Weekday Increment
No, I didn't think to do that. I forget that VEEAM keeps track of what it backs up in the database and doesn't go off windows file archive bits. Erasing the tape probably would have worked for me. I thought if I did that I'd lose what was on the tape and not be able to back it up again, as with Backup Exec, but with VEEAM that would have worked. It does seem buggy though that VEEAM would deem a full backup job that is cancelled as done and then when it is re-run it assumes it's doing an incremental. Thanks
-
- Product Manager
- Posts: 20413
- Liked: 2301 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Full Backup Cancel and then re-runs as Weekday Increment
I didn't say this is exactly what happened, I just made an assumption.It does seem buggy though that VEEAM would deem a full backup job that is cancelled as done and then when it is re-run it assumes it's doing an incremental.
Only the log analysis should clarify the situation. So, if you're willing to understand the root cause of the issue, kindly, open a ticket with our support team.
Thanks.