Hello there.
I need to adjust specific schedule for particular backup job: backup every day at 11:30, 14:30 and at 19:00. However, I couldn`t find the appropriate option. Is it even possible or should I use few backup jobs?
-
- Enthusiast
- Posts: 48
- Liked: 4 times
- Joined: Sep 09, 2015 3:12 am
- Full Name: Anatoliy Kopylov
- Contact:
-
- Product Manager
- Posts: 6551
- Liked: 765 times
- Joined: May 19, 2015 1:46 pm
- Contact:
Re: Specific schedule
Hi,
Separate jobs will create separate backup chains which might be not very convenient. I'd stick with a Windows task scheduler to start the job at the desired times. Another option is to use Backup Window combined with "Run periodically every 3 hours" option.
Thanks
Separate jobs will create separate backup chains which might be not very convenient. I'd stick with a Windows task scheduler to start the job at the desired times. Another option is to use Backup Window combined with "Run periodically every 3 hours" option.
Thanks
-
- Enthusiast
- Posts: 48
- Liked: 4 times
- Joined: Sep 09, 2015 3:12 am
- Full Name: Anatoliy Kopylov
- Contact:
Re: Specific schedule
Thanks for your reply.
And if I want to make 5 hours interval, then job would start at 00:00, then 05:00, then 10:00, then 15:00, then 20:00, then 01:00 of the next day, etc. Am I right?
If I get it right, I actually can schedule job to run every hour with such permissions and the job will start at 11:30, 14:30 and 19:30.
I really can`t understand the conception of this option. Which time would the job start? At 00:00, then 03:00, then 06:00, etc?PTide wrote: Another option is to use Backup Window combined with "Run periodically every 3 hours" option.
And if I want to make 5 hours interval, then job would start at 00:00, then 05:00, then 10:00, then 15:00, then 20:00, then 01:00 of the next day, etc. Am I right?
If I get it right, I actually can schedule job to run every hour with such permissions and the job will start at 11:30, 14:30 and 19:30.
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Specific schedule
You're getting this right, so I'd stick to the Task Scheduler, since with this option you're not getting exactly what you're after.